header-left
File #: 0008-2009    Version: 1
Type: Ordinance Status: Passed
File created: 12/29/2008 In control: Utilities Committee
On agenda: 2/9/2009 Final action: 2/10/2009
Title: To authorize the Director of Public Utilities to execute a construction contract with Jess Howard Electric Co. for construction of the Smoky Row Booster Station Motor Control Center & Pump Replacements; to authorize the transfer of $58.04 within the Water Works Enlargement Voted Bonds Fund; to authorize the appropriation and transfer of $297,857.61 from the Water System Reserve Fund to the Water Works Enlargement Voted Bonds Fund; and to authorize the expenditure of $297,915.65 from the Water Works Enlargement Voted Bonds Fund; for the Division of Power and Water. ($297,915.65)
Attachments: 1. ORD0008-2009 Bid tab.pdf, 2. ORD0008-2009 QFF.pdf, 3. ORD0008-2009 Smoky Row map.pdf, 4. ORD0008-2009 Legis. Info. Form.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
2/10/20091 MAYOR Signed  Action details Meeting details
2/10/20091 CITY CLERK Attest  Action details Meeting details
2/9/20091 Columbus City Council ApprovedPass Action details Meeting details
2/9/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
2/2/20091 Columbus City Council Read for the First Time  Action details Meeting details
1/23/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/23/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
1/23/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
1/22/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/22/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
1/22/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
1/16/20091 EBOCO Reviewer Reviewed and Disapproved  Action details Meeting details
1/14/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/13/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/13/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
1/13/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
1/12/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
1/9/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
1/9/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
1/7/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
1/7/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
1/7/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/6/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
1/6/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/5/20091 Utilities Drafter Sent for Approval  Action details Meeting details
1/2/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
12/31/20081 Utilities Reviewer Reviewed and ApprovedPass Action details Meeting details
12/30/20081 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with Jess Howard Electric Co. for the Smoky Row Booster Station Motor Control Center & Pump Replacements; in the amount of $297,915.65; and to transfer $297,857.61 from the Water System Reserve Fund to the Water Works Enlargement Voted Bonds Fund.

2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened nine bids on December 17, 2008. Bids were received from: Jess Howard Electric Co. - $297,915.65; Lake Erie Electric - $303,270; Crace Construction - $323,957.70; Claypool Electric - $343,090; Proline Electric - $346,500; Righter Co. - $364,430; Area Energy & Electric (incomplete) - $366,753.20; Affordable Choice Electric - $398,970; and Valley Electrical Consolidated - $416,130.

The lowest and best bid was from Jess Howard Electric Co. in the amount of $297,915.65. Their Contract Compliance Number is 31-4405752 (expires 1/16/11, Majority). Additional information regarding all bidders, description of work, contract time frame and detailed amounts can be found on the attached Legislation Information Form.

3. FISCAL IMPACT: This legislation includes a transfer of funds within the Water Works Enlargement Voted Bonds Fund and a transfer of funds from the Water System Reserve Fund to the Water Works Enlargement Voted Bonds Fund as a temporary measure until such time as the proceeds from a bond sale can be made available.


Title

To authorize the Director of Public Utilities to execute a construction contract with Jess Howard Electric Co. for construction of the Smoky Row Booster Station Motor Control Center & Pump Replacements; to authorize the transfer of $58.04 within the Water Works Enlargement Voted Bonds Fund; to authorize the appropriation and transfer of $297,857.61 from the Water System Reserve Fund to the Water Works Enlargement Voted Bonds Fund; and to authorize the expenditure of $297,...

Click here for full text