header-left
File #: 0187-2012    Version: 1
Type: Ordinance Status: Passed
File created: 1/23/2012 In control: Public Utilities Committee
On agenda: 3/26/2012 Final action: 3/28/2012
Title: To authorize the Director of Public Utilities to enter into a professional services agreement with Black and Veatch, Inc. for the Wastewater Treatment Facilities Multiple Hearth Incinerator Improvements Project, to authorize the transfer within the Sanitary Sewer Obligation Bond Fund of $333,470.00 and the expenditure of up to $793,976.00 from the Sanitary Sewer General Obligation Bond Fund for the Division of Sewerage and Drainage, to amend the 2011 Capital Improvements Budget; ($793,976.00).
Attachments: 1. Ord 0187-2012 Director's Legislation Information Sheet for Incincerator project1 011812, 2. Ord 0187-2012 CIP Legislation Request Form for Multiple Hearth Incinerator Improvements, 3. Ord 0187-2012 Sub-Contractor WIF 650249-1 & 650343-2 SIGNED WWTF Multiple Hearth.xls
Explanation

1. BACKGROUND:

A. Need. This legislation authorizes the Director of Public Utilities to enter into a professional services agreement with Black and Veatch, Inc. for the Wastewater Treatment Facilities Multiple Hearth Incinerator Improvements Project for the Division of Sewerage and Drainage. The WWTF Multiple Hearth Incinerator Improvements consist of CIP # 650249-100002 for $333,470.00 and CIP # 650343-100002 for $460,506.00. The estimated total project will be up to $793,976.00. The contract provides preliminary design, detailed design, and construction service; however, only Preliminary Design is included in this initial agreement with the remaining services added with subsequent contract modifications. The purpose of the Preliminary Design is to perform a condition assessment on the existing incinerators at both WWTPs and determine the scope of work required to improve reliability of the incinerator system with emphasis on determining the required air pollution control devices necessary to meet the new 2016 federal Sewage Sludge Incinerator (SSI) rule for Maximum Achievable Control Technologies. The Division has determined that these services cannot be performed by City personnel at this time, and has planned for the procurement of these services on a routine basis.

The project will be a multiyear multiphase project that will renew approximately annually with adjustments to fees and scope of work for each phase:
2012: Current Engineering Agreement $ 793,976
2012: Preliminary Design is budgeted for $ 859,000
2012: Detailed Design is budgeted for $2,560,000
2013: Construction Services is budgeted for $1,828,000
Projected Totals $6,040,976
Note: Construction services schedule to start in 2014and be completed in 2016.

B. Procurement Information: The Division advertised for a RFP on the City of Columbus's Vend...

Click here for full text