header-left
File #: 0979-2009    Version: 1
Type: Ordinance Status: Passed
File created: 6/30/2009 In control: Recreation & Parks Committee
On agenda: 7/20/2009 Final action: 7/23/2009
Title: To authorize and direct the Director of Recreation and Parks to enter into contract with Builderscape, Inc. for the Carriage Place Playground Design/ Build Services Project; to authorize the expenditure of a contract amount of $119,275.00 and contingency amount of $30,725.00 from the Private Grants Fund ($75,000.00) and from the Voted 1999/2004 Parks and Recreation Bond Fund ($75,000.00); and to declare an emergency. ($150,000.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/23/20091 CITY CLERK Attest  Action details Meeting details
7/21/20091 MAYOR Signed  Action details Meeting details
7/20/20091 Columbus City Council ApprovedPass Action details Meeting details
7/20/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
7/7/20091 Rec & Parks Drafter Sent to Clerk's Office for Council  Action details Meeting details
7/2/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
7/2/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
7/2/20091 Rec & Parks Drafter Sent for Approval  Action details Meeting details
7/2/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/1/20091 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
7/1/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
7/1/20091 Rec & Parks Drafter Sent for Approval  Action details Meeting details
7/1/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/1/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
7/1/20091 Rec & Parks Drafter Sent for Approval  Action details Meeting details
6/30/20091 Rec & Parks Drafter Sent for Approval  Action details Meeting details
6/30/20091 REC & PARKS DIRECTOR Reviewed and Approved  Action details Meeting details
6/30/20091 Rec & Parks Drafter Sent for Approval  Action details Meeting details
Explanation
Background:

This project includes the design and purchase of a universally accessible play structure at Carriage Place Park. The equipment will be installed by the community with contractor supervision and the rubberized safety surface and base material will be installed by the contractor.

Proposals were received by the Recreation and Parks Department on June 25, 2009 for the Carriage Place Playground Design/ Build Services Project, as follows:
Status Amount
Builderscapes MAJ $119,275.00
Playworld Midstates MAJ $130,000.00

Project Contingency to be included in the legislation is $30,725.00.

The community was involved with the selection of the contractor as well as the design of the play equipment. They will also be involved with the installation of the equipment.

The Contract Compliance Number for Builderscape, Inc. is #20-0537419.
Contract compliant through: 8/21/09 (they are in the process of updating)

Financial Impact:
Money is available under the Voted 1999/2004 Parks and Recreation Bond Fund, and the Private Grants Fund as follows:

Fund: 702 / Project: 510017/ OCA: 644526/ Obj Level 3: 6621 / Amount: $75,000.00
Fund: 291 / Grant: 519043 /OCA: 519043/ Obj Level 3: 6621 / Amount: $75,000.00

Title
To authorize and direct the Director of Recreation and Parks to enter into contract with Builderscape, Inc. for the Carriage Place Playground Design/ Build Services Project; to authorize the expenditure of a contract amount of $119,275.00 and contingency amount of $30,725.00 from the Private Grants Fund ($75,000.00) and from the Voted 1999/2004 Parks and Recreation Bond Fund ($75,000.00); and to declare an emergency. ($150,000.00)

Body
WHEREAS, bids were received by the Recreation and Parks Department on June 25, 2009, and the contract for the Carriage Place Playground Design/ Build Services Project was awarded to the lowest bidder; and

WHEREAS, said contrac...