Explanation
1. BACKGROUND:
A. Need. This legislation authorizes the Director of Public Utilities to enter into a construction contract with the Kenmore Construction Company, Inc. for the Fulton/Mound/Noble Combined Sewer Rehabilitation project and to authorize the transfer within and expenditure of $4,215,329.84 in funds from the Sanitary Sewer General Obligation Fund for the Division of Sewerage and Drainage.
The work for which proposals are invited consists of all labor and materials for the repair and rehabilitation of approximately 5,166 LF of 48-inch diameter and 1,118 LF of 24-inch diameter brick sewer along Fulton, Mound, and Noble streets utilizing the Cured-In-Place Pipe (CIPP) process; rehabilitation of approximately 3 brick manholes; replacement of frame and cover on 2 brick manholes; cleaning of the sewers, pre and post videos, confirmation of the status of service laterals and their reinstatement, bypass pumping; construction of approximately 28 LF of 48-inch diameter combination sewer, 444 LF of 42-inch diameter, 887 LF of 36-inch diameter, 268 LF of 30-inch diameter, 1,716 LF of 8-inch through 18-inch diameter storm sewer, manholes, and curb inlets; construction of approximately 746 LF of 8-inch diameter sanitary sewer and manholes; construction of approximately 777 LF of 8-inch and 76 LF of 6-inch diameter water main together with valves and fire hydrants; roadway improvements involving construction of ADA accessibility curb ramps, curb and sidewalk; pavement restoration, maintenance of traffic, and other such work as may be necessary to complete the contract in accordance with the plans (CC-15613) and specifications.
The project timeline is 540 days from the issuance of the Notice of Commencement and the Notice to Proceed.
B. Procurement Information: The Division advertised for Competitive Bid on the City of Columbus's Vendor Services website and in the City Bulletin in accordance with the provisions of Section 329.14 of ...
Click here for full text