Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to enter into contract with Complete General Construction for the Pedestrian Safety Improvements - Lane Avenue Sidewalks project.
The project will construct sidewalk and ADA curb ramps on the south side of West Lane Avenue from Kenny Road to Fyffe Road; mill and resurface West Lane Avenue from Kenny Road to east of Fyffe Road; and will add a left turn lane eastbound at Kenny Road and westbound at SR 315.
In addition, this project has included improvements by ODOT that will widen US 315 north and south exit ramps at West Lane Avenue and US 315 and upgrading the traffic lights within the limits of the project.
10 ADA ramps will be added or reconstructed in this project. Pedestrians would be mostly students residing in the Fisher Commons and occasionally people using the sports facilities west of Kenny Road.
The anticipated project schedule for construction begins on 6/13/11 and ends on 8/19/11.
(FRA-West Lane Avenue-Parts 1 and 2 PID 89146)
The estimated Notice to Proceed date is June 6, 2011. The contract has a completion date of August 19, 2011. The project was let by the Office of Support Services through vendor services. 1 bid was received on April 25, 2011 (1 majority) and tabulated on April 26, 2011 as follows:
Company Name Bid Amt City/State Majority/MBE/FBE
Complete General Construction $1,783,507.07 Columbus, OH Majority
Award is to be made to Complete General Construction, as the lowest, best, most responsive and most responsible bidder.
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction.
2. CONTRACT COMPLIANCE
Complete General Construction's contract compliance number is 314366382 and expires 12/15/11.
2. FISCAL IMPACT
The...