Explanation
Background: This legislation authorizes the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with Advanced Engineering Consultants, in the amount of $19, 500.00 for engineering services for the installation and relocation of three new grease traps for the Division of Fire. Advanced Engineering Consultants will be responsible for the complete design program including, but not limited to, the engineering and design of removal, relocation, and installation of three new grease traps, all associated piping, removal and/or replacement of concrete and/or asphalt and any flooring that would need to be removed in order to relocate these grease traps.
A Request for Proposals was sent to the following firms: Advanced Engineering Consultants, Dynamix Engineering Ltd., Dynotec, Inc., and Ribway Engineering. The City received two proposals, from Advanced Engineering Consultants, and Dynamix Engineering Ltd. Per City Codes 329.11, the Project Manager and Management Analyst II recommended Advanced Engineering Consultants to the Finance and Management Director. The Finance and Management Director agreed with this recommendation. Advanced Engineering Consultants was selected based on their past work on behalf of the City. The cost of this contract was negotiated with Advanced Engineering Consultants within the context of the available budget.
Emergency action is requested so that the services may proceed quickly, thereby facilitating the installation and relocation of the new grease traps to be located at Fire Stations Nos. 11, 29, and 32.
Fiscal Impact: Sufficient funding for this project is available in the Safety Voted Bond Fund. Advanced Engineering Consultants Contract Compliance #31-1612308, expiration date 07/13/2008.
Title
To authorize the Finance and Management Director to enter into contract on behalf of the Office of Construction Management with Advanced Engineering Consul...