Explanation
1. BACKGROUND:
This legislation authorizes a modification to the design contract with Korda/Nemeth Engineering, Inc. for contract document preparation and other engineering services needed during the construction phase of the Greenhill Acres Subdivision Project which is one of the Group 7 Roadside Stormwater System Improvements Projects.
The work consists of furnishing engineering services during construction of this project. This project was rebid due to contractor irregularities found in the bid documents. This in turn caused funds to be expended from the design contract which were not anticipated during design contract preparation. The additional work includes preparation of project bid manuals (for rebid of project), review of contractor bids and references for a second time, shop drawing review, plan interpretation during construction, review contractor requested field changes, prepare as-built construction drawing to the division for record purposes.
Contract Compliance No.: 31-0922991, Expiration date: 09/28/2009, Majority
2. FISCAL IMPACT:
The legislation includes a transfer of funds within the Storm Sewer Bond Fund and an amendment to the 2007 Capital Improvements Budget to allow sufficient cash and authority in the proper account for this project.
Title
To authorize the Director of Public Utilities to enter into a contract modification with Korda/Nemeth Engineering, Inc. for the Greenhill Acres Subdivision Project; to authorize the transfer of $13,524.00 within the Storm Sewer Bond Fund; to authorize the amendment of the 2007 Capital Improvements Budget; and to authorize the expenditure of $13,524.00 from the Voted Storm Sewer Bond Fund; for the Division of Sewerage and Drainage. ($13,524.00)
Body
WHEREAS, the Division of Sewerage and Drainage engineering personnel have determined it to be in the best interest of the City of Columbus to increase the contract amount to incorporate these engineering serv...
Click here for full text