header-left
File #: 1036-2008    Version: 1
Type: Ordinance Status: Passed
File created: 6/11/2008 In control: Public Service & Transportation Committee
On agenda: 7/7/2008 Final action: 7/9/2008
Title: To authorize the Public Service Director to enter into a contract for the Transportation Division with Strawser Paving Company, Inc. for construction of the 2008 Resurfacing Project 4, Neighborhood Pride project; to authorize the expenditure of $1,218,107.71 from the Streets and Highways G.O. Bonds Fund for the Transportation Division; and to declare an emergency. ($1,218,107.71)
Attachments: 1. Franklinton-Sheet 15.pdf, 2. Hilltop VII-Sheet 14.pdf, 3. Karmel Morse-Sheet 11.pdf, 4. North and South Linden-Sheet 12.pdf, 5. North Central-Sheet 13.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/9/20081 CITY CLERK Attest  Action details Meeting details
7/8/20081 MAYOR Signed  Action details Meeting details
7/7/20081 Columbus City Council ApprovedPass Action details Meeting details
7/7/20081 COUNCIL PRESIDENT Signed  Action details Meeting details
6/26/20081 Service Reviewer Sent for Approval  Action details Meeting details
6/26/20081 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
6/26/20081 Service Reviewer Sent to Clerk's Office for Council  Action details Meeting details
6/25/20081 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
6/25/20081 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
6/24/20081 Service Reviewer Sent for Approval  Action details Meeting details
6/24/20081 Auditor Reviewer Reviewed and Approved  Action details Meeting details
6/24/20081 CITY AUDITOR Reviewed and Approved  Action details Meeting details
6/24/20081 Service Reviewer Sent for Approval  Action details Meeting details
6/23/20081 Finance Reviewer Reviewed and Approved  Action details Meeting details
6/23/20081 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
6/23/20081 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
6/20/20081 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
6/13/20081 Service Drafter Sent for Approval  Action details Meeting details
6/13/20081 Service Reviewer Reviewed and Approved  Action details Meeting details
Explanation

Background: The Public Service Department, Transportation Division, routinely contracts for street resurfacing as a means of renewing and prolonging the life of streets and highways. Street resurfacing improves rideability and reduces street maintenance expenses. This legislation authorizes the Public Service Director to enter into a contract with Strawser Paving Company, Inc. in an amount up to $1,107,370.65 for the 2008 Resurfacing Project 4, Neighborhood Pride project and to pay construction inspection costs up to $110,737.06. This improvement consists of planing, asphalt overlay, concrete curb ramps, and such other work as may be necessary to complete the contract in accordance with the plans and specifications in selected Neighborhood Pride Areas of the City.

The estimated Notice to Proceed date is August 4, 2008. This project has been given 60 calendar days to complete construction.

Ten City streets will be resurfaced and 110 ADA curb ramps constructed with this project. No sidewalks will be constructed.

The Contractor has implemented and enforces an Anti-idling policy for all of its on and off road vehicles and equipment in an effort to protect the environment by reducing vehicle emissions.

The project was let by the Transportation Division and was advertised in the City Bulletin, Dodge Reports, and by the Builders Exchange. Four (4) bids were received (4 majority, 0 minority) and tabulated on June 5, 2008 as follows:

Strawser Paving Company, Inc. (low) $1,107,370.65
Decker Construction Company $1,186,044.23
Columbus Asphalt Paving, Inc. $1,209,066.64
Shelly and Sands, Inc. $1,302,300.40

Award is to be made to Strawser Paving Company, Inc. c.c. # 31-4412354 (expiring March 7, 2009), as the lowest, best, most responsive and most responsible bidder.

Emergency action is requested to allow construction to begin on or around August 4, 2008...