Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into an agreement with EMH&T in the amount of $519,840.20, to consolidate existing water tap information into a database, for the Division of Power and Water.
This project will be divided into two phases, with Phase 2 being funded through a contract modification.
Phase 1 consists of consolidating three sets of detailed water service tap information currently stored as paper cards, scanned digital images, and WASIMS into a single information database solution.
Phase 2 will be completed under a contract modification and consists of reconciling the consolidated source of tap information into a final database. This phase will help update the Water and Sewer Information Management System (WASIMS). It will also include geocoding tap information in our GIS mapping We will not know what the cost of Phase 2 will be until Phase 1 services are complete and it can be determined how much data will need to be reconciled.
2. BID INFORMATION: The selection of the firm providing the professional engineering services has been performed in accordance with the procedures set forth in Columbus City Code, Section 329.14, "Awarding professional service contracts through requests for proposals." The evaluation criteria for this contract included: 1. proposal quality, 2. experience of team, and 3. local workforce.
Requests for Proposals (RFP's) were received on March 14, 2008 from EMH&T and Unicon International. Intellinetics Inc. submitted a bid after the 4:00 closing time and was therefore rejected by the committee.
Upon review of the technical proposals, the bidders were ranked using the criteria mentioned above and EMH&T was the firm selected to perform the services for this project. Their Contract Compliance Number is 31-0685594 (expires 11/2/09, Majority). Additional information regarding both bidders, description of work, contract time frame and detaile...