Explanation
BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase the construction contract with Shelly & Sands, Inc., for the Champion Ave. 24" Water Main Project, for the Division of Power and Water.
This project consisted of constructing a 24-inch water main along Champion Avenue from Maryland Avenue to Main Street. During the construction, a number of unexpected underground utility conflicts were encountered that significantly increased the construction cost of the project. They included an abandoned gas main and a sanitary sewer which were in conflict with the alignment of the water main. Due to other utility constraints the proposed water main could not be relocated to avoid the abandoned gas main. This necessitated the removal of the gas main. There wasn't a record of the sanitary sewer, so it did not appear on the construction plans, nor was it evident in the field during construction of the water main. After the Contractor had constructed the water main, it became apparent that a sanitary sewer had been damaged by the construction. The contractor repaired the sanitary sewer, but the cost to do so, was not a part of the original contract. Finally, the Department of Public Service requested additional pavement replacement above and beyond the quantity shown on the plans approved by the Department of Public Service.
1. Amount of additional funds to be expended: $9,891.42
Original Contract Amount: $3,005,205.99
Amount of original contract and this modification: $3,015,097.41
2. Reason additional goods/services could not be foreseen:
See above.
3. Reason other procurement processes are not used:
This modification kept the contractor on the project and on schedule to finalize the water main construction. The additional cost and liability associated with bidding out this work would well exceed any benefit.
4. How cost of modification was determined:
This cost was determined by ...