header-left
File #: 0315-2012    Version: 1
Type: Ordinance Status: Passed
File created: 2/7/2012 In control: Recreation & Parks Committee
On agenda: 2/27/2012 Final action: 2/29/2012
Title: To authorize and direct the Director of Recreation and Parks to enter into contract with the Righter Company, Inc. for the Alum Creek Trail - Brittany Hills Expansion Project; to authorize the expenditure of $1,520,888.10, a contingency of $152,111.90, and $74,000 for construction inspection services for a total of $1,747,000.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($1,747,000.00)
Explanation
Background:
Bids were received by the Recreation and Parks Department on January 31, 2012 for the Alum Creek Trail - Brittany Hills Expansion Project as follows:
Status Base Bid Amount
Righter Company MAJ $1,520,888.10

The work for which proposals were invited consisted of clearing, asphalt, concrete, earthwork, landscaping, masonry, bridge construction, and other such work as may be necessary to complete the contract in accordance with the plans and specifications.

Principal Parties:
Righter Co., Inc.
Tracy Ferguson (Contact)
2424 Harrison Road
Columbus, OH 43204
614-272-9700 (Phone)
310889208 (Contract Compliance) through 2/22/13
30+ (Columbus Employees)
Emergency Justification:
An emergency exists in the usual daily operations of the Recreation and Parks Department in that it is immediately necessary to provide funding so that work can be completed during the 2012 construction season.

Fiscal Impact:
$1,747,000.00

Title
To authorize and direct the Director of Recreation and Parks to enter into contract with the Righter Company, Inc. for the Alum Creek Trail - Brittany Hills Expansion Project; to authorize the expenditure of $1,520,888.10, a contingency of $152,111.90, and $74,000 for construction inspection services for a total of $1,747,000.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($1,747,000.00)

Body
WHEREAS, bids were received by the Recreation and Parks Department on January 31, 2012 for the Alum Creek Trail - Brittany Hills Expansion Project and will be awarded to the Righter Company, Inc. on the basis of lowest and best responsive bidder; and

WHEREAS, it is necessary to enter into agreement with the Righter Company, Inc. for the Alum Creek Trail - Brittany Hills Expansion Project; and
...