File #: 0404-2012    Version: 1
Type: Ordinance Status: Passed
File created: 2/15/2012 In control: Public Utilities Committee
On agenda: 4/2/2012 Final action: 4/4/2012
Title: To authorize the Director of Public Utilities to enter into a planned contract modification with Black and Veatch for professional construction management services for the OSIS Augmentation and Relief Sewer (OARS), Phase I and II Project for the Division of Sewerage and Drainage; to transfer within $3,639,809.66 and expend up to $4,721,643.06 from the Sanitary Sewer General Obligation Fund; plus transfer within and expend up to $3,601,118.94 from the Sanitary Sewer Revenue Bond Fund; and to amend the 2011 Capital Improvements Budget. ($8,322,762.00)
Attachments: 1. Ord 0404-2012 Subcontractor Form 021712, 2. Ord 0404-2012 OARS CA Director's Legislation Information Sheet Mod 2
Explanation
A.      Need.  This legislation authorizes the Director of Public Utilities to modify the professional construction management services with Black and Veatch Corporation for the OSIS Augmentation and Relief Sewer (OARS), Phase I and II project.  The Black and Veatch Corporation modification amount requested under this ordinance is $8,322,762.00.  The total contract amount including this modification is $17,034,814. The proposed contract modification will provide construction administration and management services including construction inspection, construction and startup coordination, reporting, budgeting, scheduling, document tracking, and other related tasks to ensure the City receives a quality product in conformance with Contract Documents.   This is modification number two to the original contract. This modification covers the time period from April 2012 through March 2013. The work under Modification No. 2 will require that the firm continue providing professional construction management services for the OARS Phase I and II projects.
 
This Modification is the second of the five originally planned yearly modifications.  This Modification's time period covers April 2012 - March 2013. It is expected that future Modifications will cover years 2013, 2014 and 2015.
Amount of additional funds to be expended:  $8,322,762.00
2010 Original Contract                               $ 2,663,185.00
2011 Modification No. 1                            $ 6,048,867.00
2012 Modification No. 2 (Current)           $ 8,322,762.00
2013 Modification No. 3 (future)              $ 7,994,226.00
2014 Modification No. 4 (future)              $ 6,185,975.00
2015 Modification No. 5 (future)              $    249,423.00
CURRENT PROPOSED TOTAL              $31,464,438.00
Reasons additional goods/services could not be foreseen:  
This modification is the second of the five originally planned yearly modifications.  This modification's time period covers April 2012 - March 2013.  It is expected that future modifications will cover years 2013, 2014 and 2015.
Reason other procurement processes are not used:  
      This modification is a yearly extension of the original contract, as originally planned. The city would incur additional cost and time delays by re-bidding this process.
 
How cost of modification was determined:
The cost was determined by the Construction Management Team using the best knowledge about anticipated work during the time period covered by this Modification, available at this time.
B.      Contract Compliance No.:  43-1833073 | MAJ | Expires 10/31/2013
C.      Emergency Designation:  Emergency designation is not requested at this time.
D.      Economic Impact:  The cost of this contract modification was planned in the original contract legislation so the economic impact was minimized.
2.   FISCAL IMPACT:
This ordinance authorizes the Director of Public Utilities to transfer within $3,639,809.80 and expend up to $4,721,643.06  from the Sanitary Sewer General Obligation Fund, Fund 664, plus transfer within and expend up to $3,601,118.94 from the Sanitary Sewer Revenue Bond Fund, Fund 665, and to amend the 2011 Capital Improvements Budget to establish sufficient budget authority for this expenditure for the Division of Sewerage and Drainage.
 
Title
To authorize the Director of Public Utilities to enter into a planned contract modification with Black and Veatch for professional construction management services for the OSIS Augmentation and Relief Sewer (OARS), Phase I and II Project for the Division of Sewerage and Drainage; to transfer within $3,639,809.66 and expend up to $4,721,643.06 from the Sanitary Sewer General Obligation Fund; plus transfer within and expend up to $3,601,118.94 from the Sanitary Sewer Revenue Bond Fund; and to amend the 2011 Capital Improvements Budget. ($8,322,762.00)
 
Body
WHEREAS, the Division of Sewerage and Drainage, Department of Public Utilities, hereby requests this City Council to authorize the Director of Public Utilities to enter into planned contract modification for professional engineering services with Black and Veatch in the amount of $8,322,762.00 in order to continue to provide construction management services for the OSIS Augmentation and Relief Sewer (OARS), Phase I & II Project; and
 
WHEREAS, Contract No. EL010729 was authorized by Ordinance No. 0617-2010, as passed on May 24, 2010 for the purposes of authorizing the Director of Public Utilities to enter into a contract for professional engineering services with Black and Veatch in the amount of $2,663,185.00 in order to provide engineering services for the OSIS Augmentation and Relief Sewer (OARS), Phase 1 Project; and
 
WHEREAS, Contract No. EL011929 was authorized by Ordinance No. 0658-2011, as passed on June 06, 2011 for the purposes of authorizing the Director of Public Utilities to enter into a contract for professional engineering services with Black and Veatch in the amount of $6,048,867.00 in order to provide engineering services for the OSIS Augmentation and Relief Sewer (OARS), Phase I & II Project; and
WHEREAS, it is necessary to authorize the transfer within of $3,639,809.80 from the Sanitary Sewer General Obligation Fund, Fund 664, for purposes of providing sufficient funding for the aforementioned project expenditure; and
 
WHEREAS, it is necessary to authorize the transfer within of $3,601,118.94 from the Sanitary Sewer Revenue Bond Fund, Fund 665, for purposes of providing sufficient funding for the aforementioned project expenditure; and
 
WHEREAS, it is necessary for City Council to authorize the expenditure of funds from the Sanitary Sewer General Obligation Fund and the Sanitary Sewer Revenue Bond Fund; and
 
WHEREAS, it is necessary to amend the 2011 Capital Improvements Budget to provide sufficient authority for increasing a capital project account; and
 
WHEREAS, the Division of Sewerage and Drainage, Department of Public Utilities is requesting that this Council authorize the Director of Public Utilities to enter into planned contract modification for professional construction management services with Black and Veatch for the OSIS Augmentation and Relief Sewer (OARS), Phase I & II Project, at the earliest practical date for the preservation of the public health, peace, property, safety, and welfare; Now, Therefore,
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
Section 1.  That the Director of Public Utilities be, and hereby is, authorized to modify Contract EL010729 for professional engineering services with Black and Veatch, 4016 Townsfair Way, Suite 200, Columbus, Ohio 43219, in order to provide professional construction management services for the OSIS Augmentation and Relief Sewer (OARS), Phase I & II Project in accordance with the terms and conditions as shown in the contract modification on file in the office of the Division of Sewerage and Drainage.
 
Section 2.  That the City Auditor is hereby authorized and directed to appropriate the following funds: Dept/Div 60-05, Sewerage and Drainage | Sanitary Sewer Revenue Bond Fund | Fund 665 | Obj Lvl 3 6676
665999-100000 | Unallocated Balance | 665999 | $450.69
650491-100000 | Big Walnut/Rickenbacker San | 665491 | $232.00
 
Section 3.  That the City Auditor is hereby authorized to transfer $3,601,118.94 within the Department of Public Utilities Division of Sewerage and Drainage, Dept/Div. No. 60-05, Sewerage and Drainage Sanitary Sewer Revenue Bond Fund, Fund 665 Object Level Three 6676, as follows:
From:
Project No. | Project Name | OCA Code | change
Fund 665
650245-100000      JPWWTP B Plant Final Clarifier                  665245           -$45,507.80
650245-100000      JPWWTP B Plant Final Clarifier                      665245         -$521,571.20
650247-100000      JPWWTP A-Plant Wet Weather Hydraul.         665247      -$1,620,875.00
650250-100000      JPWWTP Biosolids Digester                        665250         -$342,809.00
650255-100000      JPWWTP Skimmings Concentrator                    665255              -$5,326.00
650350-100000      WWTP Contingencies                                  665350             -$14,395.31
650364-100000      SWWTP, New Headworks, Part 2                       665364            -$70,718.95
650404-100000      Sanitary System Rehabilitation                                 665404           -$305,118.72
650491-100000      Big Walnut/Rickenbacker San                        665491                  -$232.00
650600-100000      Franklin/Main Interceptor                           665600             -$71,452.65
650618-100000      Chestnut St Comb Sewer                                665618           -$118,772.13
650625-100000      Beulah Road Trunk Sewer Rehab                 665625             -$13,925.20
650668-100000      Torrence/Colerain                              665668               -$1,732.54
650670-100000      Beechwold/Foster Area Imps                        665670                -$3,349.67
650675-100000      Clinton Heights Imps                              665675                -$4,636.87
650676-100000      Stanton Area Sanitary Imps                          665676            -$460,245.21
665999-100000      Unallocated Balance                            665999                   -$450.69      
                                              
To:
Fund | Project No. | Project Name | OCA Code | change
665 | 650704-100001 | OSIS Augmentation and Relief Sewer (OARS), Phase 1 | 657041 | (+$3,079,547.74)
665 | 650704-100002 | OSIS Augmentation and Relief Sewer (OARS), Phase 2 | 657042 | (+$521,571.20)
 
Section 4.  That the City Auditor is hereby authorized to transfer up to $3,639,809.80 within the Department of Public Utilities Division of Sewerage and Drainage, Dept/Div. No. 60-05, Sewerage and Drainage Sanitary Sewer General Obligation Fund, Fund 664,| Object Level Three 6676, as follows:
From:
Project No. | Project Name | OCA Code | change
Fund 664
650100-100000      Sanitary Sewer Contingency                  650100      -$1,000,000.00
650360-100001      WWTP Upgrade General Program        653601      -$1,746,449.00
650333-100000      WWTPs Ash Lagoons                        664333         -$675,688.00
650250-100004      JPWWTP Biosolids Utilization          662504          -$217,672.80
To:
Fund | Project No. | Project Name | OCA Code | change
664 | 650704-100002 | OSIS Augmentation and Relief Sewer (OARS), Phase 2 | 647042 | (+$3,639,809.80)
Section 5.  That the Director of Public Utilities be and hereby is authorized to expend up to $3,601,118.94 from the Sanitary Sewer Revenue Bond Fund, Fund 665 and expend up to $4,721,643.06 from the Sanitary Sewer General Obligation Fund, Fund 664 from Division 60-05; Object Level Three 6676:
664 | 650704-100001 | OSIS Augmentation and Relief Sewer (OARS), Phase 1 | 647041 | (+$1,081,833.26)
665 | 650704-100001 | OSIS Augmentation and Relief Sewer (OARS), Phase 1 | 657041 | (+$3,079,547.74)
664 | 650704-100002 | OSIS Augmentation and Relief Sewer (OARS), Phase 2 | 647042 | (+$3,639,809.80)
665 | 650704-100002 | OSIS Augmentation and Relief Sewer (OARS), Phase 2 | 657042 | (+$521,571.20)
 
Section 6. That the 2011 Capital Improvements Budget Ordinance 0266-2011 is hereby amended as follows, to provide sufficient budget for the award of the agreement stated herein:
Fund # | Project No. | Project Name | Current Authority | Revised Authority | (Change)
665 | 650245-100000 | JPWWTP B Plant Final Clarifier | $0 | $567,079 | +$567,079 (cancellation)
665 | 650245-100000 | JPWWTP B Plant Final Clarifier | $567,079 | $521,572 | -$45,508
665 | 650247-100000 | JPWWTP A-Plant Wet Weather Hydraul | $80,000 | $1,620,875 | +$1,540,875.00 (cancellation)
665 | 650247-100000 | JPWWTP A-Plant Wet Weather Hydraul | $1,620,875 | $0 | -$1,620,875
665 | 650250-100000 | JPWWTP Biosolids Digester | $0 | $342,809  | +$342,809 (cancellation)
665 | 650250-100000 | JPWWTP Biosolids Digester | $342,809 | $0 | -$342,809
665 | 650255-100000 | JPWWTP Skimmings Concentrator | $5,326 | $0 | -$5,326
665 | 650350-100000 | WWTP Contingencies | $14,396 | $0 | -$14,396
665 | 650364-100000 | SWWTP, New Headworks, Part 2 | $70,719 | $0 | -$70,719
665 | 650404-100000 | Sanitary System Rehabilitation | $305,119 | $0 | -$305,119
665 | 650491-100000 | Big Walnut/Rickenbacker San | $0 | $232 | +$232.00 (refund)
665 | 650491-100000 | Big Walnut/Rickenbacker San | $232 | $0 | $-232.00
665 | 650600-100000 | Franklin/Main Interceptor | $71,453 | $0 | $71,453 | -$71,453
665 | 650618-100000 | Chestnut St Comb Sewer | $0 | $118,773 | +$118,773  (cancellation)
665 | 650618-100000 | Chestnut St Comb Sewer | $118,773 | $0 | -$118,773
665 | 650625-100000 | Beulah Road Trunk Sewer Rehab | $13,926 | $0 | -$13,926
665 | 650668-100000 | Torrence/Colerain | $1,733 | $0 | -$1,733
665 | 650670-100000 | Beechwold/Foster Area Imps | $3,350 | $0 | -$3,350
665 | 650675-100000 | Clinton Heights Imps | $4,637 |$0 | -$4,637
665 | 650676-100000 | Stanton Area Sanitary Imps | $460,246 | $0 | -$460,246
665 | 665999-100000 | Unallocated Balance | $19 | $451 | -$432 (cancellation)  
665 | 665999-100000 | Unallocated Balance | $451 | $0 | -$451
665 | 650245-100000 | JPWWTP B Plant Final Clarifier | $521,572 | $0 | -$521,572
665 | 650704-100001 | OSIS Augment & Relief Sewer (OARS), Ph1 | $0 | $3,079,547 | (+$3,079,547)
665 | 650704-100002 | OSIS Augmentation and Relief Sewer (OARS), Phase 2  |  $0 |$521,572 |  (+$521,572)
Creation of Authority to Match Cash
Fund # | Project No. | Project Name | Current Authority | Revised Authority | (Change)
664 | 650100-100000 | Sanitary Sewer Contingency  | $1,000,000 | $0 | -$1,000,000
664 | 650360-100001 | WWTP Upgrade General Program | $1,746,449 | $0 | -$1,746,449
664 | 650333-100000 | WWTPs Ash Lagoons | $1,120,000| $444,312 | -$675,688
664 | 650250-100004 | JPWWTP Biosolids Utilization | $266,000 | $48,327 | -$217,673
664 | 650704-100002 | OSIS Augment & Relief Sewer (OARS), Ph2 | $0 | $3,639,810 | (+$3,639,810)
Section 7.  That the said firm, Black and Veatch, shall perform the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Sewerage and Drainage.
 
Section 8.  That the City Auditor is hereby authorized to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project by monies from more than one source.
 
Section 9.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.
 
Section 10. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
 
Section 11.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.