Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to enter into a contract for the construction of the Curb Reconstruction - Citywide Curb Rehabilitation (Project 2) project.
Work for this project consists of removal and rehabilitation of various locations of curb and curb and gutter and constructing ADA curb ramps along those streets where warranted. The work consists of removing curb and replacing in kind, and other such work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.
The estimated Notice to Proceed date is October 4, 2012. The project was let by the Office of Support Services through Vendor Services and Bid Express. 4 bids were received on July 31, 2012 (4 Majority) and tabulated on August 1, 2012 as follows:
Company Name Bid Amt City/State* Majority/MBE/FBE
G&G Cement Contractors $838,519.75 Columbus, OH Majority
Columbus Asphalt Paving $840,375.25 Columbus, OH Majority
Decker Construction Company $846,494.75 Columbus, OH Majority
George J. Igel $897,262.25 Columbus, OH Majority
*City/State is from the Ohio Secretary of State web site, which may differ from the mailing address below.
The bid documents include Special Provision 146 which states, "It is the City's intent to fully utilize the available funding provided to its Curb Rehabilitation Program within the approved Capital Improvements Budget. Therefore, the City reserves the right to increase or decrease the base bid amount, up to or down to a maximum of $773,000.00. The total amount of the work and other incidentals will not exceed the total amount of the contract price (maximum of $773,000.00). In the event that the City does add c...