File #: 1100-2013    Version: 1
Type: Ordinance Status: Passed
File created: 4/26/2013 In control: Public Utilities Committee
On agenda: 6/3/2013 Final action: 6/5/2013
Title: To authorize the Director of Public Utilities to execute a planned contract modification to the professional engineering services agreement with ARCADIS U.S., Inc. for the Southerly Wastewater Treatment Plant New Headworks project; and to authorize the expenditure of $28,000.00 within the Sanitary Sewer General Obligation Bond Fund for the Division of Sewerage and Drainage, and to amend the 2013 Capital Improvement Budget. ($28,000.00).
Attachments: 1. Ord 1100-2013 CIP Legislation Request Form Mod 12, 2. Ord 1100-2013 Director's Legislation Information Sheet Mod 12, 3. Ord 1100-2013 Sub-Contractor WIF SWWTP Decommissioning Headworks 650352-100000 Signed
Explanation

1. Need. This legislation authorizes the Director of Public Utilities to modify the professional engineering services agreement with ARCADIS U.S., Inc. (formerly Malcolm Pirnie, Inc.) for the Southerly Wastewater Treatment Plant New Headworks project. The ARCADIS U.S., Inc. modification amount requested under this ordinance is $28,000.00. The total contract amount including this modification is $18,686,045.77. The proposed contract modification provides funding for detailed design services and services during construction now needed for the decommissioning of the existing headworks facilities. The potential need for this work was foreseen and so stated in the original contract's legislation, and is therefore a planned continuation of the services originally included within the existing contract's scope of service. It is not deemed either feasible or reasonable to suspend this work with the entity currently under contract and undertake continuation of these services with another provider or procurement process. The cost of the modification is a continuation of the vendor's current pricing structure, as verified by City staff.

1.1. Amount of additional funds to be expended: $28,000.00
Original Contract $ 1,567,500.00
Modification No. 1 $ 707,500.00
Modification No. 2 $ 3,060,000.00
Modification No. 3 $ 122,000.00
Modification No. 4 $ 50,000.00
Modification No. 5 $ 3,193,000.00
Cancel of Mod. 5's Balance $ (589,954.23)
Modification No. 6 $ 3,792,000.00
Modification No. 7 $ 4,614,000.00
Modification No. 8 $ 280,000.00
Modification No. 9 $ 697,000.00
Modification No. 10 $ 583,000.00
Modification No. 11 $ 582,000....