header-left
File #: 2210-2013    Version: 1
Type: Ordinance Status: Passed
File created: 9/10/2013 In control: Recreation & Parks Committee
On agenda: 9/30/2013 Final action: 10/1/2013
Title: To authorize and direct the Director of Recreation and Parks to enter into contract with Builderscape, Inc. for the Turnberry Golf Halfway House & Champion GC Shelter Project; to authorize the transfer of $83,700.00 within the Recreation and Parks Bond Fund,to amend the 2013 Capital Improvements Budget, to authorize the expenditure of $76,020.00 and a contingency of $7,680.00 for a total of $83,700.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($83,700.00)
Explanation

Background:
Bids were received by the Recreation and Parks Department on July 23, 2013 for the Turnberry Golf Halfway House & Champion GC Shelter Project, as follows:
Status Bid Amount
Builderscape MAJ $76,020
Central Ohio Building MAJ $159,000
RW Setterlin MAJ $160,255
Charter Hill Construction MAJ $237,030

Thework for which proposals are invited consists of the addition and modification to the existing Turnberry Golf Halfway House, electrical modifications to the Champion Golf Course Shelter, new drain for the Turnberry Golf Course Halfway House and other such work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.


Principal Parties:
Builderscape, Inc.
Ron Matthews (Contact)
7500 Industrial Parkway
Plain City, OH 43064
614-889-2533 (Phone)
20-0537419 compliant through: 5/3/15

Title

To authorize and direct the Director of Recreation and Parks to enter into contract with Builderscape, Inc. for the Turnberry Golf Halfway House & Champion GC Shelter Project; to authorize the transfer of $83,700.00 within the Recreation and Parks Bond Fund,to amend the 2013 Capital Improvements Budget, to authorize the expenditure of $76,020.00 and a contingency of $7,680.00 for a total of $83,700.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($83,700.00)
Body

WHEREAS, bids were received by the Recreation and Parks Department on July 23, 2013 for the Turnberry Golf Halfway House & Champion GC Shelter Project; and
WHEREAS, the contract will be awarded to Builderscape, Inc. as the lowest and best responsive bidder; and

WHEREAS, the 2013 Capital Improvement Budget will be amended to reflect the fund transfers from projects within Fund 702 in order to have funding in correct Projects for this expenditure; and

WHEREAS, funds are being moved to alternate project within Fund 712 to establish correc...