BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with J. Ranck Electric, Inc. in the amount of $762,622.14 to encumber funds in connection with the Conversion of Circuit 7217 to Circuits 14074 and 14152 Project. As part of this project existing circuit 7217 (7.2KV) shall be converted to 14.4KV and fed from existing 14.4KV circuits 14074 and 14152. All 7.2KV transformers shall be replaced with 14.4KV transformers. All hardware not 15KV class rated shall be replaced. Circuit shall be reconductored where needed and old conductor removed. Poles and crossarms shall be replaced where needed. The Division of Power shall supply all transformers. The contractor shall supply all labor, equipment and all material except transformers.
CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened three (3) bids on May 8, 2014. These bids were received from: J. Ranck Electric. - $762,622.14, US Utility, Inc. - $902,652.71, and Thayer Power - $1,115,285.55
The lowest and best bid was from J. Ranck Electric for $762,622.14. Additional information regarding each bidder, description of work, contract timeframe, detailed amounts and sub-contractors can be found on the attached Legislation Information Form.
FISCAL IMPACT: This project will expend $762,622.14 for the conversion of Circuit 7217 to Circuits 14074 and 14152 as directed by the Project Engineer, and $75,000 for inspection which will be paid from the Electric G.O. Bonds Fund.
CONTRACT COMPLIANCE INFORMATION: Contract Compliance Number, 38-2677797, expires: 4/2/2016, MAJ.
Title
To authorize the Director of Public Utilities to enter into a construction contract with J. Ranck Electric, Inc. for the Conversion of Circuits Project for the Division of Power; and to authorize the transfer of $302,716.14; to amend the 2014 Capital Improvements Budget; to authorize the expenditure of $837,622.14; and to declare an emergency...