File #: 1582-2014    Version: 1
Type: Ordinance Status: Passed
File created: 6/24/2014 In control: Public Service & Transportation Committee
On agenda: 7/21/2014 Final action: 7/23/2014
Title: To authorize the City Auditor to appropriate $150,000.00 within the Northwest Corridor/Pay as We Grow Fund; to authorize the City Auditor to transfer cash and appropriation between projects within the Northwest Corridor / Pay as We Grow Fund; to authorize the expenditure of $150,000.00 or so much thereof as may be necessary for utility relocations for the Hayden Run Boulevard, Phase II project from the Northwest Corridor Pay as We Grow Fund; and to declare an emergency. ($150,000.00)
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to pay utility relocation work by AT&T Corp. and other utilities up to the amount of $150,000 for the Hayden Run Boulevard, Phase II project.

The City of Columbus, Department of Public Service, is engaged in the Hayden Run Boulevard, Phase II Roadway Improvements project, located in Community Planning Area 01. The project limits extend Hayden Run Boulevard from its current eastern terminus eastward to Avery Road, and widen Avery Road north and south of the extension of Hayden Run Boulevard.

Hayden Run Boulevard: Hayden Run Boulevard roadway will cross the CSX railroad line via a grade separated bridge overpass. A shared use path will be installed on the north side of the roadway and a sidewalk will be installed on the south side. Street lighting will be installed. Hayden Run Boulevard will be installed with combined curb and gutter, along with storm sewer inlets and accompanying storm sewer piping. There will be raised concrete medians to the east and west of the railroad crossing. Traffic control (signage and pavement markings) will be installed. A new traffic signal installation will be installed at the intersection with Avery Road. Street trees will be provided.

Avery Road: Avery Road will be widened from 625 feet south of Hayden Run Boulevard to 590 feet north of Hayden Run Boulevard. A 2 foot wide full depth paved shoulder and a 4 foot wide turf shoulder will be provided. The existing ditch lines will be regraded. Catch basins and storm sewer piping will be installed. Traffic control (signage and pavement markings) will be installed. A new traffic signal installation will be installed at the new intersection with Hayden Run Boulevard.

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against AT&T Corp.

2. CONTRACT COMPLIANCE
The contract compliance number for AT&T Corp is 13-4924710 and ...