Title: To authorize the Director of Public Utilities to enter into an agreement with Ribway Engineering Group, Inc. for professional engineering services for the Dewberry Road Area Water Line Improvements Project for the Division of Water; to authorize a transfer and expenditure up to $352,147.12 within the Water Build America Bonds Fund; and to amend the 2015 Capital Improvements Budget. ($352,147.12)
Attachments: 1. ORD 1287-2015 Information, 2. ORD 1287-2015 Sub ID, 3. ORD 1287-2015 map
Explanation
1.  BACKGROUND:  This legislation authorizes the Director of Public Utilities to enter into an agreement with Ribway Engineering Group, Inc., for professional engineering services for the Dewberry Road Area Water Line Improvements Project, in an amount up to $352,147.12, for Division of Water Contract No. 2052.
This project includes replacing or rehabilitating approximately 20,340 linear feet of 6-inch and 8-inch water lines within the project area, which is just east of Parsons Avenue around S. R. 104.
The project is located in the Far South area (planning area 23).  The streets/roads include: Studer Avenue, Stambaugh Avenue, Curtis Street, Elwood Avenue, Bellevue Avenue, Lawndale Avenue, Glendower Avenue, Eagle Avenue, Dewberry Road, Evergreen Road, Grovewood Drive, and Augmont Avenue.
2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT:  The goal of this project is to replace or rehabilitate the existing 6-inch and 8-inch water lines that have a high break frequency.  Replacement of these water lines will improve water service, decrease burden on water maintenance operations, and reduce water loss.  The Neighborhood Liaison(s) will be contacted and informed of this project during the design phase.  Further community outreach may result through the Neighborhood Liaison Program.
3. BID INFORMATION:  The selection of the firm providing the professional engineering services has been performed in accordance with the procedures set forth in Columbus City Code, Section 329, "Awarding professional service contracts through requests for proposals."  The evaluation criteria for this contract included:  1. proposal quality and feasibility, 2. past performance, 3. environmentally preferable offeror, and 4. local workforce.
Requests for Proposals (RFP's) were received on February 6, 2015 from Ribway Engineering, CT Consultants, and Burgess and Niple.
An evaluation committee reviewed the proposals and scored them based on the criteria mentioned above.  The Department of Public Utilities recommends that the contract be awarded to Ribway Engineering Group, Inc.
The Contract Compliance Number for Ribway Engineering Group, Inc. is 31-1406579 (expires 5/12/16, MAJ).  Additional information regarding all bidders, description of work, contract time frame and detailed amounts can be found on the attached Information form.
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Ribway Engineering Group, Inc.
4. FISCAL IMPACT: A transfer of funds within the Water Build America Bonds Fund will be necessary as well as an amendment to the 2015 Capital Improvements Budget.
 
Title
To authorize the Director of Public Utilities to enter into an agreement with Ribway Engineering Group, Inc. for professional engineering services for the Dewberry Road Area Water Line Improvements Project for the Division of Water; to authorize a transfer and expenditure up to $352,147.12 within the Water Build America Bonds Fund; and to amend the 2015 Capital Improvements Budget.  ($352,147.12)
 
Body
WHEREAS, three technical proposals for professional engineering services for the Dewberry Road Area Water Line Improvements Project were received on February 6, 2015; and
WHEREAS, the Department of Public Utilities recommends that the agreement be awarded to Ribway Engineering Group, Inc.; and
WHEREAS, it is necessary for this Council to authorize the transfer and expenditure of funds within the Water Build America Bonds Fund, for the Division of Water; and  
 
WHEREAS, it is necessary to authorize an amendment to the 2015 Capital Improvements Budget for the purpose of providing sufficient spending authority for the aforementioned project expenditure; and
WHEREAS, it has become necessary in the usual daily operation of the Division of Water, Department of Public Utilities, to authorize the Director of Public Utilities to enter into a professional engineering services agreement for the Dewberry Road Area Water Line Improvements Project; for the preservation of the public health, peace, property and safety; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1.  That the Director of Public Utilities be and hereby is authorized to enter into a professional engineering services agreement for the Dewberry Road Area Water Line Improvements Project with Ribway Engineering Group, Inc., 300 East Broad Street, Suite 500, Columbus, Ohio 43215; for an expenditure up to $352,147.12; in accordance with the terms and conditions of the contract on file in the Office of the Division of Water.
SECTION 2.  That the City Auditor is hereby authorized to transfer $352,147.12 within the Department of Public Utilities, Division of Water, Dept/Div. No. 60-09, Water Build America Bonds Fund, Fund No. 609, Object Level Three 6677, as follows:
Fund No. | Project No. | Project Name | OCA Code | Change
609 | 690370-100001 (carryover) | Upground Res. P.S. & Weir | 693701 | -$352,147.12
609 | 690236-100077 (carryover) | Dewberry Rd. WL Imp's | 692377 | +$352,147.12
SECTION 3.  That the 2015 Capital Improvements Budget is hereby amended as follows:
Fund No. | Project No. | Project Name | OCA Code | Change
609 | 690370-100001 (carryover) | Upground Res. P.S. & Weir | $0 | $753,235 | +$753,235
(establish authority to match cash + future expendiutre/rounding)
609 | 690370-100001 (carryover) | Upground Res. P.S. & Weir | $753,235 | $401,087 | -$352,148
609 | 690236-100077 (carryover) | Dewberry Rd. WL Imp's | $0 | $352,148 | +$352,148
SECTION 4.  That an expenditure up to $352,147.12 is hereby authorized for the Dewberry Road Area Water Line Improvements Project within Dept/Div. 60-09, Water Build America Bonds Fund, Fund No. 609, Project No. 690236-100077 (carryover), OCA 692377, Object Level Three 6677.
SECTION 5.  That the funds necessary to carry out the purpose of this Ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.
 
SECTION 6.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.
 
SECTION 7.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.
 
SECTION 8.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.