header-left
File #: 1173-2015    Version: 1
Type: Ordinance Status: Passed
File created: 4/22/2015 In control: Public Utilities Committee
On agenda: 6/22/2015 Final action: 6/24/2015
Title: To authorize the Director of Public Utilities to modify, increase and extend the contract with Stantec Consulting Services, Inc. for Geographic Information System (GIS) Sewer Lateral Data Conversion Services for the Department of Public Utilities, and to authorize the expenditure of $3,672.49 from the Electricity Operating Fund, $23,359.49 from the Water Operating Fund, $26,189.12 from the Sewerage & Drainage Operating Fund, and $6,983.77 from the Stormwater Operating Fund. ($60,204.87)
Attachments: 1. ORD 1173-2015 GIS Swr Laterals - Mod #1, 2. ORD 1173-2015 GIS Swr Laterals - Mod #1 - Change Order Ltr, 3. ORD 1173-2015 Stantec Subs.pdf
Explanation

The Department of Public Utilities entered into a contract with Stantec Consulting Services, Inc. for Geographic Information System (GIS) Sewer Lateral Data Conversion Services for the Division of Sewerage and Drainage, which was authorized by ordinance 2520-2013. The intent of this project is to use existing sewer permits to create a sewer lateral layer for the GIS which will provide more analytical capabilities for the GIS, as well as create a more efficient method for displaying the sewer permits via the GIS which is not currently available. This project supports the directives of the Department of Public Utilities Technology Master Plan dated August 2004.

The original contract was based on the number of hours estimated to be required, based on the number of sewer laterals that would be converted. It has been determined that there are 22,300 more laterals than had been originally estimated. Based on the increase in the number of laterals, Stantec Consulting Services, Inc. projects that it will require an additional 727 hours to address the additional laterals. An additional $60,204.87 will be required to fund these additional hours. This modification No. 1 will add $60,204.87 to the original contract amount of $600,000.00 for a total contract amount of $660,204.87 and extend the contract completion date through December 31, 2015.

1. Amount of additional funds: The amount of the additional funds needed for this contract modification No. 1 is $60,204.87. The original contract EL015194 was established for $600,000.00. The total cost of the original contract and this modification is $660,204.87. The modification represents funding added during the contract period for costs related to the services provided. The need for increased funding is to cover anticipated contract billings during fiscal year 2015.

2. Reason additional needs were not forseen: The additional funds are needed because the initial estimate of sewer laterals included in t...