File #: 2484-2015    Version: 1
Type: Ordinance Status: Passed
File created: 9/27/2015 In control: Public Utilities Committee
On agenda: 11/16/2015 Final action: 11/18/2015
Title: To authorize the Director of Public Utilities to enter into a planned modification (Mod #2) to the engineering agreement with CDM Smith Inc. for professional engineering services for the Wastewater Treatment Facilities Instrumentation and Control (I&C) Integration and Programming Team project; to authorize the appropriation and transfer of funds from the Sanitary Sewer Reserve Fund to the Sanitary Sewer General Obligation (G.O.) Bond Fund and to authorize the expenditure of $500,000.00 from the Sanitary Sewer General Obligation (G.O.) Bond Fund. ($500,000.00)
Attachments: 1. Ord 2484-2015 Mod2_LegislationB_CIP348.3_08252015 (2).pdf, 2. Ord 2484-2015 Mod2_CIP348 3_CDMSMITH_Subcontractor_Form_08252015.pdf
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to modify (Mod #2) an engineering agreement with CDM Smith Inc. for professional engineering services for the Wastewater Treatment Facilities Instrumentation and Control (I&C) Integration and Programming Team project. The services to be provided are professional engineering and technical services necessary for the DPU’s SCADA, Telemetry, and Process Control Systems. The actual project specific detailed design and construction will generally be accomplished by others. CDM Smith, Inc. will provide technical and engineering assistance to the City as requested, during the design and construction efforts. The Scope of Work for this project will consist of the following tasks: (1) Project Management; (2) Project Development Assistance; (3) Project Integration; (4)

Project Integration to Servers; (5) Intra-Site Integration; (6) Daily Engineering and Technical Support; and (7) Training. Note: for additional information regarding the various Scope of Work Tasks please see the attachment: Director’s Information Sheet, Section 5.

2. MODIFICATION INFORMATION:

Amount of additional funds to be expended: $500,000.00

2013 Original Contract $349,988.00
2014 Modification #1 $711,635.00
2015 Current Modification #2 $500,000.00
2016 Future Modification #3 $500,000.00
Estimated Total $2,061,623.00

Reasons additional goods/services could not be foreseen:
This Contract Modification No. 2 was planned and anticipated, and so stated in the original contract’s legislation. It is a planned continuation of the services originally included within the existing contract’s scope of service.

Reason other procurement processes are not used:
In so much as the majority of this work was planned for and anticipated within the original procurement, and due to the highly complex and technical nature of the engineering assistance provided to the City, it is not reasonable or...