header-left
File #: 2707-2015    Version: 1
Type: Ordinance Status: Passed
File created: 10/23/2015 In control: Public Utilities Committee
On agenda: 11/23/2015 Final action: 11/24/2015
Title: To authorize the Director of Public Utilities to enter into a planned modification of the professional engineering services agreement with MWH Americas, Inc. for the Hap Cremean Water Plant (HCWP) UV Disinfection Project; for the Division of Water; and to authorize an expenditure up to $1,392,500.00 from the Water Works Enlargement Voted Bonds Fund. ($1,392,500.00)
Attachments: 1. ORD 2707-2015 Information, 2. ORD 2707-2015 Sub ID, 3. ORD 2707-2015 map
Explanation

1. BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase the professional engineering services agreement with MWH Americas, Inc. for the Hap Cremean Water Plant (HCWP) UV Disinfection Project, Division of Water Contract No. 2025.

This project will provide UV disinfection at the HCWP which will allow it to operate with a multi-barrier disinfection process (both chemical and physical disinfection).

The original contract provided funds for Preliminary Design Services (Phase I).

This Contract Modification (Mod No. 1) will establish funding for Detailed Design (Phase II) and Bidding (Phase III) Services.

Detailed Design (Phase II) will prepare construction contract documents (including specifications and drawings) for the construction of the proposed facilities. Detailed Design also includes plan and specification review meetings, assisting in negotiations, permitting, other matters with government agencies as necessary, and coordination with the DRWP UV Disinfection project.

Bidding Services (Phase III) includes assisting at the Pre-Bid Conference and bid opening, tabulating bids, making an award recommendation for lowest and best bid, and preparing Conformed to Contract documents.

1.1 Amount of additional funds to be expended: $1,392,500.00
Original Contract Amount: $ 936,618.63 (EL016478)
Modification No. 1 (current): $1,392,500.00
Total (Orig. + Mod. 1) $2,329,118.63

1.2. Reasons additional goods/services could not be foreseen:
This is the first modification to the contract and was fully explained in the original legislation under Ordinance No. 2094-2014.

1.3. Reason other procurement processes are not used:
This contract was anticipated to be funded in phases as indicated in the original request for proposals and as authorized legislation under Ordinance No. 2094-2014. MWH Americas is familiar with the details of the project and have compiled a Preliminary Design Report detailing their fi...