File #: 2874-2015    Version: 1
Type: Ordinance Status: Passed
File created: 11/6/2015 In control: Public Utilities Committee
On agenda: 12/14/2015 Final action: 12/16/2015
Title: To authorize the Director of Public Utilities to modify and extend the contract with Stantec Consulting Services, Inc. for professional engineering services for the NPDES Stormwater Permit Wet Weather Monitoring Project for the Division of Sewerage and Drainage, Stormwater and Regulatory Management Section. ($0.00)
Attachments: 1. ORD 2874-2015 NPDES Wet Weather Monitoring Mod #3 - Subcontractor Work ID Form.pdf, 2. ORD 2874-2015 - NPDES - Wet Weather Mod. 3 - Add'l info.pdf

Explanation

 

The purpose of this legislation is to authorize the Director of Public Utilities to modify the contract with Stantec Consulting Services, Inc. for professional engineering services for the NPDES Stormwater Permit Wet Weather Monitoring Project for the Division of Sewerage and Drainage, Stormwater and Regulatory Management Section.  The City’s Stormwater NPDES permit requires the City to monitor discharges from its municipal separate storm sewer system (MS4) during wet weather events.  The permit specifically requires the City to monitor wet weather discharges from three city outfalls once each quarter.  Monitoring services performed under this project will allow the City to meet its permit obligations.

 

The Director of Public Utilities accepted proposals on May 25, 2012.  Two (2) proposals were received.  The City’s latest Stormwater NPDES permit, issued by Ohio EPA, became effective on May 1, 2012.  The permit requires that storm water outfall monitoring tasks associated with this project be initiated six (6) months from the effective date of the permit and continue throughout the permit monitoring and reporting period (2013-2018).  The Division entered into contract with Stantec Consulting Services, Inc. for the entire scope of services and associated project implementation for the entire 5-year permit term.  The contract language allowed for the request of future additional budget appropriations for this contract through future contract modifications, based on funding availability, to cover the total overall cost of this project throughout the 2013-2018 contract period.  The contract period for this modification is through February 12, 2017.  All terms and conditions of the original agreement remain in full force and effect.

 

 

SUPPLIER:  Stantec Consulting Services, Inc. (11-2167170), Expires September 10, 2017

Stantec Consulting Services, Inc. does not hold MBE/FBE status.

 

The company is not debarred according to the Excluded Party Listing System of the Federal Government or prohibited from being awarded a contract according to the Auditor of State Unresolved Findings for Recovery Certified Search.

 

1.                     Amount of additional funds:  Total amount of additional funds needed for this contract modification No. 3 is $0.00.  Total contract amount including this modification is $450,000.00.

 

2.                     Reason additional funds were not foreseen:  Additional funds are not being requested at this time.

 

 

3.                     Reason other procurement processes not used:  Work under this modification is a continuation of services included in the scope of the original bid contract.  No lower pricing/more attractive terms and conditions are anticipated at this time.

 

4.                     How cost was determined:  The cost, terms and conditions are in accordance with the original agreement.

 

FISCAL IMPACT:  $0.00 is budgeted and needed for this contract modification.

 

$  88,558.23 spent as of October 30, 2015

$104,185.10 spent in 2014

$114,245.28 spent in 2013

 

 

Title

 

To authorize the Director of Public Utilities to modify and extend the contract with Stantec Consulting Services, Inc. for professional engineering services for the NPDES Stormwater Permit Wet Weather Monitoring Project for the Division of Sewerage and Drainage, Stormwater and Regulatory Management Section.  ($0.00)

 

 

Body

 

WHEREAS, the City’s latest Stormwater NPDES permit, issued by Ohio EPA, became effective on May 1, 2012.  The permit requires that storm water outfall monitoring tasks associated with this project be initiated six (6) months from the effective date of the permit and continue throughout the permit monitoring and reporting period (2013-2018), and

 

WHEREAS, the Director of Public Utilities accepted proposals on May 25, 2012, two (2) proposals were received, and

 

WHEREAS, based on the evaluation of the proposals, the Division of Sewerage and Drainage, Stormwater and Regulatory Management Section selected the best proposal submitted by Stantec Consulting Services, Inc. for the entire scope of services and associated project implementation, and

 

WHEREAS, the results of this project will attempt to characterize the seasonal types and levels of chemical constituents that are discharged from the City’s storm sewer system, and

 

WHEREAS, the contract language allows for contract modifications which funding will be requested in the Stormwater System Operating Budgets, and

 

WHEREAS, the Stormwater Management Section must continue to provide the EPA with monitoring reports without facing any penalties, and

 

WHEREAS, this modification is effective through February 12, 2017, and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Sewerage and Drainage, to authorize the Director of Public Utilities to modify and extend the contract for professional engineering services, for the NPDES Stormwater Permit Wet Weather Monitoring Project, for the immediate preservation of the public health, peace, property and safety; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities be and is hereby authorized to modify and extend EL013908 with Stantec Consulting Services, Inc., 1500 Lake Shore Dr., Suite 100, Columbus, OH 43204, to allow for the continuation of services for the contract period through and including February 12, 2017.  Total amount of additional funds needed for this contract modification No. 3 is ADD $0.00.  Total contract amount including this modification is $450,000.00.

 

SECTION 2.  That this modification is in accordance with the relevant provisions of Chapter 329 of the Columbus City Codes relating to contract modifications.  

 

SECTION 3.  That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated and the City Auditor shall establish such accounting codes as necessary. 

 

SECTION 4.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.