File #: 2664-2016    Version: 1
Type: Ordinance Status: Passed
File created: 10/14/2016 In control: Public Utilities Committee
On agenda: 11/21/2016 Final action: 11/23/2016
Title: To authorize the Director of Public Utilities to enter into a contract modification (Mod #1) with DLZ Ohio, Inc. for a construction administration and inspection services contract; to authorize the expenditure of up to $1,740,942.78 from the Sanitary Sewer General Obligation Bond Fund; and to declare an emergency. ($1,740,942.78)
Attachments: 1. Ord 2664-2016 Director's Legislation Info Sheet DLZ, 2. Ord 2664-2016 DAX Finanicals DLZ CACI Mod 1, 3. Ord 2664-2016 SWIF BP Clintonville Cooke Glenmont Area Green, 4. Ord 2664-2016 SWIF BP Clintonville Schreyer Springs, 5. Ord 2664-2016 SWIF BP Hilltop Lining Project, 6. Ord 2664-2016 SWIF Central College Subtrunk of Big Walnut
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into contract modification (Mod #1) of a construction administration and construction inspection (CA/CI) services contract with DLZ Ohio, Inc. DLZ has provided Construction Administration/Inspection (CA/CI) Services for Division of Sewerage and Drainage Capital Improvement Projects throughout the City of Columbus. The services for this contract modification include oversight of projects during construction to ensure that work performed by the construction contractor conforms to project plans and specifications. The CA/CI services include review of contractor requests for information, track and review force account work, aid in developing solutions to problems that arise during construction, and interact with residents to answer questions or resolve issues.

2. PROJECT MODIFICATION:
Amount of additional funds to be expended: $1,740,942.78

2.1 Original Contract (EL017142) $1,500,000.00
Modification # 1 $1,740,942.78
Total $3,240,942.78

2.2 Reasons additional goods/services could not be foreseen:
This is a planned contract modification that provides funds for continued construction inspection and construction administration of Division of Sewerage and Drainage Capital Improvement Projects.

2.3 Reason other procurement processes are not used:
This is a planned contract modification of a multi-year contract. Due to the sheer volume of construction work performed the Division of Sewerage and Drainage has CA/CI Service Contracts with 3 firms each contract is a multi-year. This is the last year for the current set contracts.

2.4 How cost of modification was determined:
The modification amount is based on full time inspection of the various construction projects, the anticipated duration of the various construction projects, and estimated administrative oversight needed for...

Click here for full text