Title: To authorize the Director of Public Utilities to modify (Mod #3) the professional engineering services agreement with Chester Engineers, Inc. for the Jackson Pike Wastewater Treatment Plant Corrosion Prevention and Protective Coating Systems Project; to authorize the transfer of $187.15 and the expenditure of up to $200,187.80 in funds from the Sanitary Sewer General Obligation Bond Fund, and amend the 2016 Capital Improvements Budget. ($200,187.80).
Attachments: 1. Ord 2944-2016 SWIP Corrosion Prevention Protective Coating Mod #3 650259-100001, 2. Ord 2944-2016 Mod #3 - CIP 259.1 Directors Information 10-31-16, 3. Ord 2944-2016 DAX Financial Coding 650259-1
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to modify (Mod #3) the professional engineering services agreement with Chester Engineers, Inc. for the Jackson Pike Wastewater Treatment Plant Corrosion Prevention and Protective Coating Systems Project, Project 650259-100001 for the Division of Sewerage and Drainage. It has been determined that the protective coatings on many structures, buildings and process items at the Jackson Pike Wastewater Treatment Plant are in need of rehabilitation. This project has prepared a study to determine the specific areas, structures, and process items in need of rehabilitation, and determine the steps necessary to inhibit deterioration in the future. The Scope of Work for this project, at the City’s discretion, consists of the following elements:

A. Conduct a detailed survey of the condition of the coatings and determine the required remedies for:
1. Buildings, both interior and exterior, and structures.
2. Process and general equipment, including control panels.
3. Piping systems, including gate and valve operators.
4. Conduit systems.

B. Prepare a report with determinations on the survey results and recommendations.
C. Prepare a General Corrosion Prevention and Protective Coating Specification.
D. Prepare electronic bid documents for Corrosion Prevention and Protective Coating applications to the locations selected by the City. Three construction contracts are planned for the work.
E. Provide services during construction.

The detailed survey, Condition Assessment Report, and the specification have been completed. The project contracting plan determined. The actual emplacement of the work will be by construction contract. The first of three Corrosion Prevention and Protective Coating construction contracts, Contract J218, has been completed. The second of three Corrosion Prevention and Protective Coating construction contracts, Contract J219, is in contract closeout. The third of...