File #: 3363-2016    Version: 1
Type: Ordinance Status: Passed
File created: 12/22/2016 In control: Public Utilities Committee
On agenda: 1/30/2017 Final action: 2/1/2017
Title: To authorize the Director of Public Utilities to enter into a planned modification for the Professional Construction Management II Services agreement with AECOM Technical Services, Inc. for the Division of Water; to authorize a transfer and an expenditure up to $1,506,000.00 within the Water General Obligations Bond Fund; and to authorize an amendment to the 2016 Capital Improvements Budget. ($1,506,000.00)
Attachments: 1. ORD 3363-2016 Information, 2. ORD 3363-2016 SWIF, 3. ORD 3363-2016 Funding

Explanation

 

1. BACKGROUND:  This Ordinance authorizes the Director of Public Utilities to modify and increase the Professional Construction Management II (PCM II) Services Agreement with AECOM Technical Services, Inc., in an amount up to $1,506,000.00, for the Division of Water. 

 

Work performed to date includes design phase construction management (CM) services for multiple capital improvement projects including: program management, constructability reviews, construction cost estimating, project coordination, and construction scheduling. 

 

Future phasing will continue design phase CM services and begin construction phase CM services that include program management, field representation/inspection, material inspection and testing, PLC programming and controls integration services, O&M ready support services, assistance with claims negotiation, small business outreach, and PMIS support services.  These services will be provided through the end of each construction project included in the PCM program.

 

2. CONTRACT DURATION / FUTURE MODIFICATIONS:  Future contract modifications are expected as this multi-year contract provides support services to multiple construction projects that begin construction within the 2017 through 2020 period, with services extending through the end of construction.  The contract is estimated to be complete by 2022, however, extensions may be needed based on actual construction schedules.

 

Contract modification #1 (current) is needed to provide design phase CM and/or construction phase services for the six projects listed below:

 

                                          690486-100000 - HCWP Hypochlorite Conversion

                     690487-100000 - PAWP Hypochlorite Conversion

                     690519-100000 - HCWP Standby Power

                     690520-100000 - DRWP Standby Power

                     690535-100000 - DRWP UV Disinfection

                     690536-100000 - HCWP UV Disinfection

                     690553-100000 - AS-Authorized Contingency

 

A description of these projects can be found on the attachment “ORD 3363-2016 Information, Item No. 9”.

 

All projects have a "Citywide" planning area as they service several central Ohio communities.

 

2.1 Amount of additional funds to be expended:  $1,506,000.00

Original Contract Amount:                     $    618,000.00                     (PO003180, -3188, -3196, -3199, -3202, -3205, -3208)

Modification 1 (current)                     $ 1,506,000.00

Total (Orig. + Mod 1)                     $ 2,124,000.00

 

2.2. Reasons additional goods/services could not be foreseen:  

This modification was planned and identified in the Request for Proposal (RFP) and the original contracting legislation Ord. No. 0003-2016, which called for services to be provided by the selected PCM team over a multi-year period.

 

2.3. Reason other procurement processes are not used: 

The original RFP and the initial authorizing legislation Ord. No. 0003-2016 anticipated services over a multi-year period to maintain continuity and consistency through the project construction periods and to provide coordination between projects.  The current PCM team is familiar with the details of the multiple construction projects underway.  The process of selecting and contracting a new PCM team to oversee these construction projects would likely impact construction progress and increase construction costs.

 

2.4. How cost of modification was determined:

The consultant prepared a cost breakdown exhibit including estimated hours and hourly rates for upcoming work.  The breakdown was reviewed and approved by the Project manager for the Columbus Division of Water. 

 

3. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: 

This project which will facilitate the Construction Administration/Inspection services for projects in the Division of Water’s capital program.  These projects are all related to the drinking water supply and treatment systems.  These projects are incorporated in the capital improvement program for various reasons including meeting regulatory requirements, improving the reliability of the City’s drinking water supply, and enhancing worked and public safety.  All of these functions are tied to the economic vitality of the service area.  Outreach activities will be performed under this contract to encourage small / minority business participating in the construction contacts.  The consultant team has identified a commitment to the Mayor’s Green Initiative in their business practices.

 

4. CONTRACT COMPLIANCE INFO:  95-2661922, expires 9/19/18, Majority, DAX Vendor No: 010897.

 

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against AECOM Technical Services, Inc.

 

5. FISCAL IMPACT:  A transfer of funds within the Water G.O. Bonds Fund will be necessary as well as an amendment to the 2016 Capital Improvements Budget.

 

Title

 

To authorize the Director of Public Utilities to enter into a planned modification for the Professional Construction Management II Services agreement with AECOM Technical Services, Inc. for the Division of Water; to authorize a transfer and an expenditure up to $1,506,000.00 within the Water General Obligations Bond Fund; and to authorize an amendment to the 2016 Capital Improvements Budget.  ($1,506,000.00)

 

Body

 

WHEREAS, Ordinance No. 0003-2016, passed February 1, 2016, authorized the Director of Public Utilities to enter into contract with AECOM Technical Services, Inc. for the Division of Water; and

 

WHEREAS, Modification No. 1 is needed in order to provide necessary services for six Division of Water projects including: DRWP and HCWP Standby Power, DRWP and HCWP UV Disinfection, HCWP Hypochlorite Conversion, and PAWP Hypochlorite Conversion; and

 

WHEREAS, it is necessary to authorize the City Auditor to transfer and expend funds within the Water G.O. Bonds Fund; and

 

WHEREAS, it is necessary to authorize an amendment to the 2016 Capital Improvements Budget for purposes of providing sufficient funding and expenditure authority for the aforementioned project expenditures; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Water, to authorize the Director of Public Utilities to modify and increase the Professional Construction Management II Services agreement with AECOM Technical Services, Inc., for the preservation of the public health, peace, property, safety and welfare; now, therefore,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities is hereby authorized and directed to modify and increase the Professional Construction Management II Services agreement with AECOM Technical Services, Inc. in the amount of $1,506,000.00.

 

SECTION 2.  That this contract modification is in compliance with Chapter 329 of Columbus City Codes.

 

SECTION 3. That the transfer of $665,000.00 or so much thereof as may be needed, is hereby authorized between projects within Fund 6006 - Water G.O. Bond Fund, per the account codes in the attachment to this ordinance.

 

SECTION 4.  That the 2016 Capital Improvements Budget is hereby amended, in Fund 6006, Water G.O. Bonds Fund, as follows:

 

Project ID | Project Name | Current Authority | Revised Authority | Change

P690553-100000 (New) | PCM-II | $1,750,000 | $1,085,000 | -$665,000

P690486-100000 (New) | HCWP Disinf. Imp’s | $587,000 | $631,000 | +$44,000

P690487-100000 (New) | PAWP Disinf. Imp’s | $589,800 | $668,800 | +$79,000

P690520-100000 (New) | DRWP Standby Power | $0 | $542,000 | +$542,000

 

SECTION 5. That the expenditure of $1,506,000.00 or so much thereof as may be needed, is hereby authorized in Fund 6006 - Water G.O. Bonds Fund, in Object Class 06, Capital Outlay, per the accounting codes in the attachment to this ordinance.

 

SECTION 6.  That the funds necessary to carry out the purpose of this Ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 7.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

 

SECTION 8.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

SECTION 9.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.

 

SECTION 10.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.