Title: To amend the 2016 Capital Improvement Budget; to authorize and direct the City Auditor to transfer cash and appropriation within the Streets and Highways Bond Fund; to authorize the Director of the Department of Public Service to enter into a construction agreement with Camp Chase Railway in connection with the Pedestrian Safety Improvement - Wilson Road Shared Use Path - Broad Street to Sullivant Avenue project; to authorize the expenditure of up to $60,000.00 within the Streets and Highways Bond Fund, Fund 7704; and to declare an emergency. ($60,000.00)
Attachments: 1. 0237-2017 Construction Agreement Account Codes.pdf
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to enter into a construction agreement with Camp Chase Railway in association with the Pedestrian Safety Improvement - Wilson Road Shared Use Path - Broad Street to Sullivant Avenue project.

The City of Columbus, Department of Public Service, is engaged in the Pedestrian Safety Improvement - Wilson Road Shared Use Path - Broad Street to Sullivant Avenue project, C.I.P. No. 590105-100083. The project objectives are to construct a pedestrian shared use path within the existing right of way from Sullivant Avenue north to Broad Street. Planned improvements include the construction of a shared use path (SUP) on the west side of Wilson Road from Sullivant Avenue to Broad Street, located in the Hilltop Area (Community Planning Area 15). Modifications will be made to the existing bridge and the alignment of the roadway to accommodate the path addition. The roadway will be widened north of Fremont Street to accommodate a southbound left turn lane. Opposite the new turn lane, a raised grassed median will be placed between Fremont and Wilson Park Way to support a path crossing at Freemont Street.

It is necessary to contract with Camp Chase Railway for work to be performed on or near the railroad. Camp Chase Railway will provide construction engineering and inspection work concerning its property as part of the project. The railroad will also provide flagmen, watchmen, and other protective services and devices to promote safety and continuity of train operations during the project. There is also a need for temporary track realignment and final track alignment as part of the project. The construction agreement will reimburse Camp Chase Railway the costs associated with these activities.

2. CONTRACT COMPLIANCE INFORMATION
The contract compliance number for Camp Chase Railway is 007076, TIN 35-1922133, and is currently not contract compliant. We have contacted them and they wil...