File #: 0019-2017    Version: 1
Type: Ordinance Status: Passed
File created: 1/2/2017 In control: Public Utilities Committee
On agenda: 3/13/2017 Final action: 3/16/2017
Title: To authorize the Director of Public Utilities to modify a professional engineering services agreement with ARCADIS U.S. Inc., in connection with the Sewer System Capacity Model Update 2012; to authorize the transfer of $1,576,174.90 within and a total expenditure of up to $3,075,175.32 from the Sanitary Sewer General Obligation Fund; and to authorize an amendment to the 2016 Capital Improvements Budget. ($3,075,175.32)
Attachments: 1. Ord 0019-2017 Director's Legislation Information Sheet 460.1 mod2, 2. Ord 0019-2017 5. Schedule 2A-1 (SWIF) Subcontractor Work ID Form 12122016, 3. Ord 0019-2017 DAX Financials SSCM Update Mod 2
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to modify (Mod #2) a professional engineering services agreement with ARCADIS U.S. Inc. for the Sewer System Capacity Model Update 2012 Project for the Division of Sewerage and Drainage. The initial contract covered work for the first year with four subsequent annual contract modifications planned. This modification is needed to perform model applications, monitoring and data management, refinement of the sanitary model, stormwater model, real time control and system operation, deliverables and Blueprint Columbus Integrated Plan support.

The sewer collection system model developed and enhanced by the Model Update Project, is the principle tool used to manage the planning and operations of the City’s sewer collection system. Enhancement of this tool is vital to minimizing sewer overflows and backups and thereby minimizing negative impacts to the environment caused by the City’s sewer system. The continual updating of this model is also necessary to ensure compliance with the City’s consent orders with the Ohio Environmental Protection Agency.

MODIFICATION INFORMATION:
1.1 Amount of additional funds to be expended: $3,075,175.32

Original contract: $4,326,563.00
Modification #1 $5,328,048.34
Modification #2 $3,075,175.32
Current Total: $12,729,786.66
Future
Modification #3 $2,000,000.00

1.2. Reasons additional goods/services could not be foreseen:
This is a multi-year agreement with planned modifications.

1.3. Reason other procurement processes are not used:
Uninterrupted support of the Blueprint Columbus Integrated Plan program is critical and work completed to date would have to be repeated if this project was rebid.

1.4. How cost of modification was determined:
A Cost Summary was submitted by the Consultant and reviewed and approved by Department personnel.

2. Project Task Description: Overall project scope elements:

· Upda...