Title: To authorize the Director of Public Utilities to enter into a planned modification of the professional services agreement with EMA, Inc. for the Advanced Metering System Study and Implementation Project; for the Division of Water; to authorize a transfer and expenditure up to $550,000.00 from the Water General Obligations Bond Fund; and to authorize an amendment to the 2016 Capital Improvements Budget. ($550,000.00)
Attachments: 1. ORD 0797-2017 Information, 2. ORD 0797-2017 SWIF, 3. ORD 0797-2017 Funding

Explanation

 

1.0 BACKGROUND:  This Ordinance authorizes the Director of Public Utilities to modify and increase the professional services agreement with EMA, Inc. for the Advanced Metering System (AMS) Study and Implementation Project, Division of Water Contract No. 2073.

 

The entire project consists of four (4) Phases.  Original authorizing Ordinance No. 1597-2015 indicated the agreement will be modified an additional three (3) times, however, the Department now expects additional modifications.  Phases 3 and 4 will require multiple modifications due to the complex nature of the scope and to provide funding in accordance with projected Capital Improvements Budget and Bond Sales.

 

Modification No. 1 (current) is needed to procure Phase 2 services.  In this phase, EMA will prepare a Request for Proposal (RFP) for an AMS system that clearly defines the City’s objectives and requirements.

 

1.1 Amount of additional funds to be expended:  $550,000.00

Original Contract Amount:                     $369,077.71                     (EL017444)

Modification  No. 1 (current):                     $550,000.00

Total (Orig. + Mod. 1)                     $919,077.71

 

1.2. Reasons additional goods/services could not be foreseen:  

This is a planned modification as indicated in the original authorizing legislation (Ordinance No. 1597-2015).  Additional modifications are expected during Phases 3 and 4.

 

1.3. Reason other procurement processes are not used: 

Modifications to the agreement were planned as part of the original Request for Proposals RFP.  Additionally, the current consultant is familiar with the project and has completed all the work to-date.  Bidding the work to another consultant will further delay the project and will result in higher costs due to bringing the new consultant up to speed on the project.  

 

1.4. How cost of modification was determined:

A cost proposal was provided by EMA, Inc.  The proposal was reviewed by Department staff and deemed acceptable.

 

2.0 FUTURE CONTRACT MODIFICATION(S):  Future modifications are anticipated to complete Phases 3 and 4 of the project.  Phase 3 services will coordinate the vendor selection process and Phase 4 services will provide program management assistance during implementation of the AMS system.

 

The planning area is “City Wide” because this project serves multiple planning areas.

 

3.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: 

An AMS program is favorable to the DPU’s operations and customer service function, as replacing older water and electrical meters will improve service, decrease burden on maintenance operations, reduce water loss, and improve revenue.  Moving from quarterly to monthly billing will have a positive impact on customers as the bills will be more manageable in both cost and time

 

4.0 CONTRACT COMPLIANCE INFO:  41-1467091, expires 3/24/19, Majority. DAX Vendor No. is 007843.

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against EMA, Inc.

 

5.0 FISCAL IMPACT:  A transfer of funds within the Water G.O. Bond Fund will be necessary as well as an amendment to the 2016 Capital Improvements Budget.

 

 

Title

 

To authorize the Director of Public Utilities to enter into a planned modification of the professional services agreement with EMA, Inc. for the Advanced Metering System Study and Implementation Project; for the Division of Water; to authorize a transfer and expenditure up to $550,000.00 from the Water General Obligations Bond Fund; and to authorize an amendment to the 2016 Capital Improvements Budget.  ($550,000.00)

 

 

Body

 

WHEREAS, Contract No. EL017444 was authorized by Ordinance No. 1597-2015, passed July 20, 2015, was executed on August 21, 2015, and approved by the City Attorney on September 2, 2015, for the Advanced Metering System Study and Implementation Project; and

 

WHEREAS, Contract Modification No. 1 (current) will establish funding for Phase 2, preparing a Request for Proposal (RFP); and

 

WHEREAS, future modifications are expected to procure funds for the vendor selection process and to provide program management assistance during implementation of the AMS system; and

 

WHEREAS, it is necessary to authorize the Director of Public Utilities to modify and increase the professional services agreement with EMA, Inc. for the Advanced Metering System Study and Implementation Project; and

 

WHEREAS, it is necessary to authorize a transfer and expenditure of funds within the Water G.O. Bond Fund, for the Division of Water; and 

 

WHEREAS, it is necessary to authorize an amendment to the 2016 Capital Improvements Budget for purposes of providing sufficient funding and expenditure authority for the aforementioned project expenditure; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Water, to authorize the Director of Public Utilities to modify and increase the professional services agreement with EMA, Inc., for the Advanced Metering System Study and Implementation Project, for the preservation of the public health, peace, property, safety and welfare; now, therefore,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities is hereby authorized and directed to modify and increase the professional services agreement with EMA, Inc. for the Advanced Metering System Study and Implementation Project, in an amount up to $550,000.00.

 

SECTION 2.  That this contract modification is in compliance with Chapter 329 of Columbus City Codes.

 

SECTION 3. That the transfer of $50,000.00 or so much thereof as may be needed, is hereby authorized between projects within Fund 6006 - Water G.O. Bond Fund, per the account codes in the attachment to this ordinance.  (There is already $500k in Fund 6006, Project 690358-100000.)

 

SECTION 4.  That the 2016 Capital Improvements Budget is hereby amended in Fund 6006 - Water G.O. Bond Fund, as follows:

 

Project No. | Project Name | Revised Authority | Remaining Authority | Change

P690236-100092 (NEW) | S. Hampton WL Imp's | $232,634 | $232,636 | +2 (establish authority to match cash)

P690236-100092 (NEW) | S. Hampton WL Imp's | $232,636 | $228,118 | -$4,518

P690236-100095 (NEW) | Valleyview Dr. WL Imp's | $4,706 | $4,707 | +$1 (establish authority to match cash)

P690236-100095 (NEW) | Valleyview Dr. WL Imp's | $4,707 | $0 | -$4,707

P690411-100008 (NEW) | Watershed Demo. Pt 2 | $200,000 | $159,224 | -$40,776

P690358-100000 (NEW) | Water Meter Renewal | $500,000 | $550,001 | +$50,001

 

SECTION 5. That the expenditure of $550,000.00 or so much thereof as may be needed, is hereby authorized in Fund 6006 - Water G.O. Bonds Fund, in Object Class 06, Capital Outlay, per the accounting codes in the attachment to this ordinance.

 

SECTION 6.  That the funds necessary to carry out the purpose of this Ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 7.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

 

SECTION 8.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

SECTION 9.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.

 

SECTION 10.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.