Title: To authorize the Director of Public Service to execute an agreement with, and accept monies from Cugini & Capoccia Builders, Inc. (CCBI), relative to the Signal Installation - Central College Road at Harlem Road project; to, as necessary, provide a refund to CCBI after the project and final accounting are complete; and to declare an emergency. ($0.00)
Explanation
1. BACKGROUND
This ordinance authorizes the Director of the Department of Public Service to execute a contribution agreement with and accept monies from Cugini & Capoccia Builders, Inc. (CCBI) relative to the Signal Installation - Central College Road at Harlem Road project, and to, as necessary, provide a refund to CCBI after the project and final accounting are complete.

The aforementioned project consists of various improvements to Central College Road and Harlem Road, including: installing of a new traffic signal at the intersection of Central College Road and Harlem Road; widening Central College Road to three lanes 300’ in either direction to provide a left turn lane on the east and west legs; designing the intersection radii on Harlem Road to accommodate future widening; and constructing a 5’ sidewalk along the south side of Central College Road through the entire project area to connect the existing walkway at the east and west termini.

CCBI has agreed to fund a portion of the costs associated with the proposed turn lane improvements.

2. FISCAL IMPACT
CCBI will contribute $117,795.51 to support the completion of the aforementioned project.

3. EMERGENCY DESIGNATION
Emergency action is requested in order to allow for immediate execution of agreements necessary to facilitate the design and construction of said public improvements in a timely manner.

Title
To authorize the Director of Public Service to execute an agreement with, and accept monies from Cugini & Capoccia Builders, Inc. (CCBI), relative to the Signal Installation - Central College Road at Harlem Road project; to, as necessary, provide a refund to CCBI after the project and final accounting are complete; and to declare an emergency. ($0.00)

Body
WHEREAS, the Department of Public Service proposes constructing various improvements to Central College Road and Harlem Road, including: installing a new traffic signal at the intersection of Central College Road and Harlem...

Click here for full text