File #: 2300-2017    Version: 1
Type: Ordinance Status: Passed
File created: 8/25/2017 In control: Health & Human Services Committee
On agenda: 9/18/2017 Final action: 9/20/2017
Title: To authorize the Board of Health to issue a Change Order to the existing contract with Tyler Technologies, Inc., to provide DAX related services and equipment to its Central Cashier Office; to authorize the expenditure of up to $16,630.00 from the Health Operating Fund; and to declare an emergency ($16,630.00).
Attachments: 1. ORD2300-2017DAX, 2. Tyler Technologies Info for K Mod 2300 17, 3. Tyler Technologies Chg Ord 2017-02 for Ord 2300 17
Explanation

BACKGROUND: This Ordinance authorizes the Board of Health to issue a Change Order to the contract with Tyler Technologies, Inc. for the Dynamics AX 2012 Financial Management System, in the amount of $16,630.00. This Change Order is needed to provide system engineering services and equipment necessary to meet CPH cashiering needs, to ensure proper, accurate payment processing services to the CPH Central Cashier Office. The modification will cover hardware and implementation costs.

1.1 Amount of additional funds to be expended: $16,630.00
Original Contract Amount: $5,619,677.00
Tyler Change Order 2015-10: $ 97,774.00
Tyler Change Order 2017-02: $ 16,630.00
Total (Orig. + CO.1 + CO.2) $5,734,081.00

1.2. Reasons additional goods/services could not be foreseen:
The scope of work was not part of the original contract, as the legacy financial management system did not include cashiering for Columbus Public Health and the desire for a new cashiering solution did not arise until after the Tyler contract was in place.

1.3. Reason other procurement processes are not used:
Tyler Technologies has been performing the development of this highly technical financial management system for the past three years and are intimately involved in the configuration and implementation. It would take another vendor considerable amount of time and cost to become familiarized with the intricate configuration of this part of the integration to our Centralized Cashier Office before conceptualizing a seamless roll-out.

1.4. How cost of modification was determined:
The consultant prepared an estimate based on the scope of work, and City staff reviewed and approved this cost estimate.

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: The new Dynamics AX 2012 Financial Management System replaced the City’s Performance Series system on January 1, 2016. The latest significant update to Performance was in 2008 and the...

Click here for full text