File #: 2714-2017    Version: 1
Type: Ordinance Status: Passed
File created: 10/6/2017 In control: Public Utilities Committee
On agenda: 11/20/2017 Final action:
Title: To authorize the Director of Public Utilities to modify its construction contract with Decker Construction Company for utility cut and restoration services for the Division of Sewerage & Drainage; and to authorize the expenditure of $100,000.00 from the Sanitary Sewer Operating Fund. ($100,000.00)
Attachments: 1. 2714-2017 Funding Attachment

Background

 

This legislation authorizes the Director of Public Utilities to modify its construction contract for utility cut and restoration services with Decker Construction Company for an additional $100,000.00.  Various types of utility excavations are performed within the City of Columbus' right-of-way by the Department of Public Utilities.  The restoration work typically involves repair of existing pavement, curbs, and sidewalks in a manner conforming to the City of Columbus, Construction and Material Specifications (CMSC).  The Department routinely outsources this restoration work to a contractor that is equipped and trained to make these repairs.  Typical types of restoration work that require outsourcing involve the installation of wheelchair ramps, asphalt repair involving thermalbond heatweld repairs, asphalt milling machines capable of full width milling, and the delivery of flowable controlled density fill using volumetric mixer trucks.

 

CONSTRUCTION CONTRACT AWARD:  The Director of Public Utilities publicly opened one bid on February 24, 2016 from Decker Construction Company.

 

Decker Construction Company's bid was deemed the lowest, most responsive and responsible bid.  Their Contract Compliance Number is 31-0983557 (expires 10/13/17, Majority).  The contract contains a multi-year renewal option. 

 

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Decker Construction Company.

 

FISCAL IMPACT:  $100,000.00 is budgeted and needed for this purchase.

 

Amount of additional funds:  Total amount of additional funds needed for this contract modification is $100,000.00.  Total contract amount including this modification is $3,010,952.50 (original contract: $1,460,622.50, modification 1: $1,450,330.00, this modification: $100,000.00).

 

Reasons additional funds were not foreseen:  The Division of Sewerage and Drainage has had a number of emergency projects come up during the year.

 

Reason other procurement processes were not used:  Work under this modification is a continuation of services included in the scope of the original bid contract.  No lower pricing/more attractive terms and conditions are anticipated at this time.

 

How cost was determined:  The cost, terms, and conditions are in accordance with the original agreement.

 

The following amounts were encumbered in 2014, 2015, 2016, and 2017 year-to-date for similar services:

 

2017 YTD: $1,450,330.00

2016: $1,460,622.50

2015: $1,705,813.81

2014: $1,415,581.76

 

Title

 

To authorize the Director of Public Utilities to modify its construction contract with Decker Construction Company for utility cut and restoration services for the Division of Sewerage & Drainage; and to authorize the expenditure of $100,000.00 from the Sanitary Sewer Operating Fund.  ($100,000.00)

 

Body

 

WHEREAS, one bid for the Utility Cut Restorations - 2016 Project was received and publicly opened in the offices of the Director of Public Utilities on February 24, 2016; and

 

WHEREAS, the sole bid from Decker Construction Company, in the amount of $1,460,622.50 for the first year of the contract, was deemed the lowest, most responsive, and responsible bid; and

 

WHEREAS, the contract with Decker Construction Company contained a multi-year renewal option; and

 

WHEREAS, the contract with Decker Construction Company was previously modified in 2017 in the amount of $1,450,330.00; and

 

WHEREAS, the Department of Public Utilities now seeks to modify the contract by authorizing the expenditure of an additional $100,000.00 for the Division of Sewerage & Drainage without extending the term of the contract; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities to authorize the Director to modify its construction contract with Decker Construction Company for utility cut and restoration services, for the preservation of the public health, peace, property and safety; now therefore,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities be and hereby is authorized to modify its construction contract for utility cut and restoration services with Decker Construction Company, 3040 McKinley Avenue, Columbus, Ohio 43204; in the amount of $100,000.00; in accordance with the terms and conditions of the contract on file in the Department of Public Utilities.

 

SECTION 2.  That the expenditure of $100,000.00 or so much thereof as may be needed, is hereby authorized in Fund 6100 Sewer Operating Sanitary Fund, Object Class 03 Services per the accounting codes in the attachment to this ordinance.

 

SECTION 3.  That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated and the City Auditor shall establish such accounting codes as necessary.

SECTION 4.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.