File #: 2993-2017    Version: 1
Type: Ordinance Status: Passed
File created: 11/3/2017 In control: Public Service & Transportation Committee
On agenda: 12/4/2017 Final action:
Title: To amend the 2017 Capital Improvement Budget; to authorize the City Auditor to transfer cash and appropriation within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into a professional services contract with JMT (Johnson, Mirmiran &Thompson), Inc. for the UIRF - South Linden Sidewalks 2017 project; to authorize the expenditure of up to $167,186.12 from the Streets and Highways Bond Fund to pay for this contract; and to declare an emergency. ($167,186.12)
Attachments: 1. ORD2993-2017 UIRF S Linden Sidewalks design
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to enter into professional services contracts with JMT (Johnson, Mirmiran &Thompson), Inc., in the amount of up to $167,186.12 for the UIRF - South Linden Sidewalks 2017 project.

The intent of this project is to provide the Department of Public Service with continuing, contractual access to additional resources that are necessary to perform various professional engineering, survey, and technical expertise for the department to implement projects for the Department of Development through the City’s Urban Infrastructure Recovery Fund (UIRF) program.
The Department of Public Service, Office of Support Services, solicited Requests for Proposals for the UIRF - South Linden Sidewalks 2017, CIP 440005-100070; UIRF - Far South Engineering 2017, CIP 440005-100071; and UIRF - Sidewalks and Roadway Improvements 2017, CIP 440005-100072 contracts. One RFP was issued for three projects with the intention of awarding the three projects to three companies. The project was formally advertised on the Vendor Services web site from July 11, 2017, to August 10, 2017. The City received seventeen (17) responses. All proposals were deemed responsive and were fully evaluated when the Evaluation Committee met on August 23, 2017. The responding firms were:

Company Name City/State Majority/MBE/MBR/F1/AS1/PHC
Prime AE Columbus, OH AS1
Strand Columbus, OH Majority
JMT Columbus, OH Majority
E.L. Robinson Columbus, OH Majority
CHA Consulting Columbus, OH Majority
The Mannik & Smith Group Columbus, OH Majority
DLZ Ohio Worthington, OH MBR
CCI Engineering Columbus, OH F1
AECOM Columbus, OH Majority
Ribway Engineering Columbus, OH MBE
Moody Engineering Columbus, OH MBE
HDR Columbus, OH Majority
ADR Columbus, OH Majority
Fishbeck, Thompson, Carr & Huber Columbus,...