header-left
File #: 3112-2017    Version: 1
Type: Ordinance Status: Passed
File created: 11/14/2017 In control: Public Service & Transportation Committee
On agenda: 12/4/2017 Final action:
Title: To amend the 2017 Capital Improvement Budget; to authorize the transfer of funds between projects within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project; to authorize the expenditure of up to $143,796.66 for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project; and to declare an emergency. ($143,796.66)
Attachments: 1. ORD3112 2017 4th at Northwood const.pdf

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Service to enter into contract with Complete General Construction Company for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project and to provide payment for construction, construction administration and inspection services.

 

This contract consists of the construction of a traffic Pedestrian Hybrid Beacon, curb ramps, signage, pavement markings, and other such work as may be necessary to complete the contract in accordance with the drawings, technical specifications, plans at 3346 Drawer E, and City of Columbus Construction and Material specifications set forth in the Invitation For Bid (IFB).

 

The estimated Notice to Proceed date is January 4, 2018.  The project was let by the Office of Support Services through Vendor Services and Bid Express.  One bid was received on November 7, 2017 (one majority) and tabulated as follows:  

     

Company Name                                             Bid Amount      City/State                                   Majority/MBE/FBE

Complete General Construction Company          $125,040.58                     Columbus, Ohio                                          Majority

  

Award is to be made to Complete General Construction Company as the lowest responsive and responsible and best bidder for their bid of $125,040.58.  The amount of construction administration and inspection services will be $18,756.08.  The total legislated amount is $143,796.66.

 

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction Company.

 

2.  CONTRACT COMPLIANCE INFORMATION

The contract compliance number for Complete General Construction Company is CC006056 and expires 8/31/2019.

 

3.  PRE-QUALIFICATION STATUS

Complete General Construction Company and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

 

4.  FISCAL IMPACT

This is a budgeted item within the Department of Public Service’s 2017 Capital Improvement Budget.  Funds in the amount of $143,796.66 are available for this project in Fund 7704, the Streets and Highways Bond Fund.  An amendment to the 2017 Capital Improvement Budget is required to establish sufficient budget authority for the project.

5.  EMERGENCY DESIGNATION

Emergency action is requested in order to complete needed improvements at the earliest possible time to meet project timelines and to ensure the safety of the travelling public.

Title

To amend the 2017 Capital Improvement Budget; to authorize the transfer of funds between projects within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project; to authorize the expenditure of up to $143,796.66 for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project; and to declare an emergency.  ($143,796.66)

 

Body

WHEREAS, the Department of Public Service is engaged in the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project; and 

 

WHEREAS, the work for this project consists of the construction of a traffic Pedestrian Hybrid Beacon, curb ramps, signage, pavement markings, and other such work as may be necessary to complete the contract in accordance with the drawings, technical specifications, and plans at 3346 Drawer E and City of Columbus Construction and Material specifications set forth in the Invitation For Bid (IFB); and

 

WHEREAS, the Department of Public Service requires funding to be available for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project for construction expenses along with construction administration and inspection services; and

 

WHEREAS, it is necessary to amend the 2017 Capital Improvement Budget to establish authority within the correct project; and

 

WHEREAS, it is necessary to authorize a transfer of funds within Fund 7704, the Streets and Highways Bond Fund, to establish sufficient cash to pay for the project; and

 

WHEREAS, Complete General Construction Company will be awarded the contract for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project; and

 

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Service in that it is immediately necessary to authorize the Director to enter into contract with Complete General Construction Company to ensure project timelines are met, thereby preserving the public health, peace, property, safety and welfare; now, therefore:

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the 2017 Capital Improvements Budget authorized by ordinance 1124-2017 be amended as follows to establish  sufficient authority for this project:

 

Fund / Project  / Project Name / Current  / Change /C.I.B. as Amended

7704 / P540007-100000 / Traffic Signal Installation - General Engineering (Voted Carryover) / $213,037.00 / ($143,797.00) / $69,240.00

 

7704 / P540007-100055 / Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue (Voted Carryover) / $0.00 / $143,797.00 / $143,797.00

 

SECTION 2.  That the transfer of $143,796.66, or so much thereof as may be needed, is hereby authorized within Fund 7704 (Streets and Highways Bond Fund),  from Dept-Div 5912 (Division of Design and  Construction), Project P540007-100000 (Traffic Signal Installation - General Engineering ), Object Class 06 (Capital Outlay) to Dept-Div 5912 (Division of Design and Construction), Project P540007-100055 (Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue), Object Class 06 (Capital Outlay).

 

SECTION 3.  That the Director of Public Service be and is hereby authorized to enter into a construction services contract with Complete General Construction Company, 1221 East Fifth Avenue, Columbus, Ohio, 43219, for the Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue project in the amount of up to $125,040.58 in accordance with the specifications and plans on file in the Office of Support Services, which are hereby approved; and to pay for necessary construction administration and inspection costs associated with the project up to a maximum of $18,756.08.

 

SECTION 4.  That the expenditure of $143,796.66, or so much thereof as may be needed, is hereby authorized in Fund 7704 (Streets and Highways Bond Fund),  Dept-Div 5912 (Division of Design and Construction), Project P540007-100055 (Signal Installation - Pedestrian Hybrid Beacon - North Fourth Street at East Northwood Avenue), Object Class 06 (Capital Outlay) per the account codes in the attachment to this ordinance.

 

SECTION 5.  That the funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 6.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 7.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 8.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor or ten days after passage if the Mayor neither approves nor vetoes the same.