header-left
File #: 0882-2018    Version: 1
Type: Ordinance Status: Passed
File created: 3/20/2018 In control: Public Utilities Committee
On agenda: 4/16/2018 Final action: 4/18/2018
Title: To authorize the Director of Public Utilities to enter into a construction contract with K & W Roofing, Inc. for the Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW; to authorize the transfer within and the expenditure of up to $1,421,429.00 from the Sanitary Sewer General Obligation Bond Fund; and to amend the 2017 Capital Improvements Budget. ($1,421,429.00)
Attachments: 1. Ord 0882-2018 SCP 03FW Director's Legislation Information Sheet (9-8-14), 2. Ord 0882-2018 SCP 03FW Sub-Contractor Work Identification Form, 3. Ord 0882-2018 DAX Financial Form 650234-9

Explanation

 

BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with K & W Roofing, Inc. for the Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW, CIP 650234-100009. The work consists of removal to the deck of the existing roofing system, the repair or replacement of any damaged roof deck, and the installation of a new lightning protection system and other such work as may be necessary to ensure that the building is watertight and any other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, and City of Columbus Construction and Material Specifications as set forth in the Invitation for Bid (IFB).

 

PROJECT TIMELINE: All work shall be substantially complete within one hundred twenty calendar days of the Notice to Proceed, with final completion to occur within one hundred fifty (150) calendar days. The City anticipates issuing a Notice to Proceed on or about June 7, 2018.

 

PROCUREMENT INFORMATION: The Division advertised for competitive bids submission for the subject services on the City's Vendor Services website and in the City Bulletin in accordance with the overall provisions of Chapter 329 of the Columbus City Code. The Division of Sewerage and Drainage received two (2) bids on March 14, 2018 from the following companies:

 

Name                                                 C.C. No.   Exp. Date  Vendor #   City/State    Status                     

K&W Roofing, Inc.                             31-1606825 6/7/18       005659     Pataskala, OH    MAJ

Kalkreuth Roofing / Sheet Metal, Inc.   55-0647319 7/11/19     009276  Lewis Center, OH MAJ

 

K & W Roofing, Inc. was awarded the project based on the Bid Tabulation and Quality Factor Form evaluation process results. 

 

EMERGENCY DESIGNATION is not requested for this project.

 

CONTRACT COMPLIANCE NO: 31-1606825 | Exp.  6/7/2018 | MAJ | Vendor # 005659

ECONOMIC / ENVIRONMENTAL IMPACT: Roof replacement of a failed roofing system provides watertight environmental controls to the important process equipment and building components housed in the structure. Removal and replacement of the failed equipment, electronic, and electrical components would be a major impact to the budget. No community outreach or environmental factors are considered for this project.

FISCAL IMPACT: This legislation authorizes the transfer within and expenditure of up to $1,421,429.00 from the Sanitary Sewer General Obligation Bond Fund, Fund 6109 and amends the 2017 Capital Improvements Budget.

 

Title

 

To authorize the Director of Public Utilities to enter into a construction contract with K & W Roofing, Inc. for the Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW; to authorize the transfer within and the expenditure of up to $1,421,429.00 from the Sanitary Sewer General Obligation Bond Fund; and to amend the 2017 Capital Improvements Budget. ($1,421,429.00)

 

Body

 

WHEREAS, the Division of Sewerage and Drainage advertised for competitive bids for roof removal and replacement for the Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW, CIP 650234-100009, two (2) bids were received; and 

 

WHEREAS, it was determined that K & W Roofing, Inc. should be awarded the project based on the results of the Bid Tabulation and Quality Factor Form evaluation; and 

 

WHEREAS, it is necessary to authorize the transfer within and the expenditure of up to $1,421,429.00 from the Sanitary Sewer General Obligation Bond Fund, Fund 6109; and

 

WHEREAS, it is necessary to authorize the amendment to the 2017 Capital Improvements Budget; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Sewerage and Drainage, to authorize the Director to enter into a construction contract with K & W Roofing, Inc., for the Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW, for the immediate preservation of the public health, peace, property and safety; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1: That the Director of Public Utilities is hereby authorized to enter into a construction contract with K & W Roofing, Inc., 8356 National Road, Pataskala, Ohio 43062 for the Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW, CIP 650234-100009 in accordance with the terms and conditions of the contract on file in the Office of the Division of Sewerage and Drainage.

 

SECTION 2. That the transfer of $1,421,429.00 is hereby authorized in  the Sanitary Sewer General Obligation Bond Fund 6109 per the accounting codes attached to this ordinance.

 

SECTION 3. That the expenditure of up to $1,421,429.00 or so much thereof as may be needed, is hereby authorized per the accounting codes in the attachment to this ordinance.

 

SECTION 4. That the 2017 Capital Improvements Budget is hereby amended as follows:

 

Fund | Project No. | Project Name | Current Authority | Revised Authority | (Change)

6109 | P650725-100011 | Lrg. Dia. Blacklick Creek Main Trunk | $1,200,000 | $0 | (-$1,200,000)

6109 | P650725-100005 | Big Walnut Trunk Sewer North | $100,000 | $0 | (-$100,000)

6109 | P650725-100010 | West Side Trunk Rehabilitation | $128,926 | $7,497 | (-$121,429)

6109 | P650234-100009 | Sewer Maintenance Operations Center (SMOC) Roof Replacement Project, Phase 2, SCP 03FW | $0 | $1,421,429 | (+$1,421,429)

 

SECTION 5. That the said firm, K & W Roofing, Inc., shall perform the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Sewerage and Drainage.

 

SECTION 6. That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

 

SECTION 7. That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

SECTION 8. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts of contract modifications associated with this ordinance.

 

SECTION 9. That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 10. That this ordinance shall take effect and be in force from and after the earliest period allowed by law.