File #: 1283-2018    Version: 1
Type: Ordinance Status: Passed
File created: 4/30/2018 In control: Recreation & Parks Committee
On agenda: 6/4/2018 Final action: 6/7/2018
Title: To authorize the Director of Recreation and Parks to enter into settlement agreements with Shaw & Holter, Inc., and Jones-Stuckey Ltd. for the Academy Park Suspension Bridge project; to accept paid settlements in the amount of $300,000.00 to the Recreation and Parks Permanent Improvement Fund; and to declare an emergency. ($300,000.00)
Explanation

This legislation authorizes the Director of Recreation and Parks to execute a settlement agreement and mutual release with Shaw & Holter, Inc., and Jones-Stuckey Ltd. for the Academy Park Suspension Bridge project.

The City undertook a rehabilitation of the Academy Park Suspension Bridge. Shaw & Holter and Jones-Stuckey teamed together and were selected to provide services for the project. The parties entered into a contract dated March 14, 2013.

After the project was completed, the bridge experienced a cable failure on April 15, 2015. A dispute arose with respect to the cause, liability, and cost to repair the bridge.

Shaw and Holter, Inc., will pay the City of Columbus Department of Recreation and Parks $80,000 to compensate for the additional costs associated with the repairs.

Jones-Stuckey Ltd., will pay the City of Columbus Department of Recreation and Parks $220,000 to compensate for the additional costs associated with the repairs.

Emergency Justification: Emergency action is requested in order to proceed with settlement agreement and release immediately for the City of Columbus to receive reimbursement for the repair cost.

Fiscal Impact: Settlement funding received shall be deposited to Fund 7747. $300,000.00 will be deposited to the Recreation and Parks Permanent Improvement Fund 7747.

Title

To authorize the Director of Recreation and Parks to enter into settlement agreements with Shaw & Holter, Inc., and Jones-Stuckey Ltd. for the Academy Park Suspension Bridge project; to accept paid settlements in the amount of $300,000.00 to the Recreation and Parks Permanent Improvement Fund; and to declare an emergency. ($300,000.00)

Body

WHEREAS, the City undertook a rehabilitation project of the Academy Park Suspension Bridge with the team of Shaw & Holter, as the contractor, and Jones-Stuckey, as the engineer. The parties entered into a contract dated March 14, 2013; and

WHEREAS, after the project was completed, the bridge ...