Title: To authorize the Director of Public Utilities to enter into a construction contract with Kenmore Construction Co., Inc. for the Dublin Road Water Plant (DRWP) Standby Power Project; to authorize the appropriation and transfer of $10,681,257.50 from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund; to authorize the appropriation and expenditure of $10,681,257.50 from the Water Supply Revolving Loan Account Fund; to authorize a transfer and expenditure up to $2,000.00 within the Water General Obligation Voted Bonds Fund; to provide for payment of prevailing wage services to the Department of Public Service, Design and Construction Division; for the Division of Water; and to authorize an amendment of the 2018 Capital Improvements Budget. ($10,683,257.50)
Attachments: 1. ORD 1624-2018 Bid Tab, 2. ORD 1624-2018 QFF, 3. ORD 1624-2018 Information, 4. ORD 1624-2018 Utilization Form, 5. ORD 1624-2018 Funding, 6. ORD 1624-2018 map
Explanation

1.0 BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with Kenmore Construction Co., Inc. for the Dublin Road Water Plant (DRWP) Standby Power Project, in an amount up to $10,681,257.50, for Capital Improvements Project No. 690520-100000, Division of Water Contract Number 2075.

Funds in the amount of $2,000.00 will also be encumbered with the Department of Public Service for Prevailing Wage services.

This construction contract will install two standby power generators at the Dublin Road Water Plant (DRWP). These generators will allow the plant to continue to operate during utility power outages, thereby improving the reliability of the water supply system.

Other work will include installation of a switchgear enclosure, concrete encased duct bank, miscellaneous site work, and a fuel offloading area with spill containment. The project will also include modifying the bio-retention pond and the existing plant systems for network, fire alarms, and intercom to integrate new enclosures into the system.

Community Planning Area: “NA” since the DRWP serves several communities.

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: This project will provide the residents of the City of Columbus and a large part of Franklin County with a reliable supply of clean water for potable water use and fire protection during electric utility power outage. This project benefits the economy by providing uninterrupted water service and fire protection during a region-wide power outage.

Public informational meetings are not anticipated for this project because all proposed work is anticipated to occur within the boundaries of the water plant. Regulatory agencies will be notified of the proposed work as appropriate.

3.0 CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened three (3) bids on May 9, 2018 from:

1. K...