Title: To amend the 2018 Capital Improvement budget; to authorize the Director of Public Service to enter into contract with Complete General Construction for the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project; to authorize the expenditure of up to $357,216.35 from the Streets & Highways Bond Fund for the project; and to declare an emergency. ($357,216.35)
Attachments: 1. ORD 1706-2018 Thornapple const

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Service to enter into contract with Complete General Construction for the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project and to provide payment for construction, construction administration and inspection services. 

 

This contract includes removing and replacing the existing traffic signal at the intersection of Westerville Road at Thornapple Drive and Wallingford Avenue.  Improvements also include traffic control, guardrail, curb ramps, pavement removal, and pavement replacement for utility crossings.

 

The estimated Notice to Proceed date is July 31, 2018.  The project was let by the Office of Support Services through Vendor Services and Bid Express.  Five bids were received on June 7, 2018, and tabulated as follows:  

     

Company Name                                 Bid Amount               City/State                                         Majority/MBE/FBE    

Complete General Construction          $310,622.91             Columbus, OH                     Majority

U.S. Utility Contractor                       $312,913.73             Columbus, OH                     FBE

Asplundh Construction, LLC              $333,053.34             Columbus, OH                                       Majority

Jess Howard Electric Company          $407,399.61                        Blacklick, OH                                                                     Majority

M P Dory Co                                    $412,378.89             Columbus, OH                              Majority

 

Award is to be made to Complete General Construction as the lowest responsive and responsible and best bidder for their bid of $310,622.91.  The amount of construction administration and inspection services will be $46,593.44.  The total legislated amount is $357,216.35.

 

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction.

 

2. CONTRACT COMPLIANCE INFORMATION

The contract compliance number for Complete General Construction is CC006056 and expires 8/31/19.

 

3. PRE-QUALIFICATION STATUS

Complete General Construction and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

 

4.  FISCAL IMPACT

This is a budgeted expense.  Funds in the amount of $357,216.35 are available within Fund 7704, the Streets & Highways Bond Fund.    An amendment to the 2018 Capital Improvement Budget is required to establish sufficient budget authority for the project.

5. EMERGENCY DESIGNATION

Emergency action is requested in order to complete needed improvements at the earliest possible time to ensure the safety of the travelling public.

Title

To amend the 2018 Capital Improvement budget; to authorize the Director of Public Service to enter into contract with Complete General Construction for the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project; to authorize the expenditure of up to $357,216.35 from the Streets & Highways Bond Fund for the project; and to declare an emergency. ($357,216.35)

 

Body

WHEREAS, the Department of Public Service is engaged in the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project; and 

 

WHEREAS, the work for this project consists of removing and replacing the existing traffic signal at the intersection of Westerville Road at Thornapple Drive and Wallingford Avenue.  Improvements also include traffic control, guardrail, curb ramps, pavement removal, pavement replacement for utility crossings, and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents; and

 

WHEREAS, Complete General Construction will be awarded the contract for the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project; and

 

WHEREAS, the Department of Public Service requires funding to be available for the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project for construction expense along with construction administration and inspection services; and

 

WHEREAS, it is necessary to amend the 2018 Capital Improvement Budget to establish authority within the correct project; and

 

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Service in that it is immediately necessary to enter into contract with Complete General Construction to ensure the safety of the travelling public, thereby preserving the public health, peace, property, safety and welfare; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1. That the 2018 Capital Improvements Budget authorized by ordinance 1010-2018 be amended as follows to establish  sufficient authority for this project:

 

Fund / Project  / Project Name / Current  / Change /C.I.B. as Amended

7704 / P540007-100000 / Traffic Signal Installation - General Engineering (Voted Carryover) / $414,507.00 / ($357,217.00) / $57,290.00

 

7704 / P540007-100056 / Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue (Voted Carryover) / $0.00 / $357,217.00 / $357,217.00

 

SECTION 2.  That the Director of Public Service be and is hereby authorized to enter into a construction services contract with Complete General Construction, 1221 E. 5th Avenue, Columbus, Ohio  43219, for the Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue project in the amount of up to $310,622.91 in accordance with the specifications and plans on file in the Office of Support Services, which are hereby approved; and to pay for necessary construction administration and inspection costs associated with the project up to a maximum of $46,593.44.

 

SECTION 3.  That the expenditure of $357,216.35, or so much thereof as may be needed, is hereby authorized in Fund 7704 (Streets & Highways Bond Fund), Dept-Div 5913 (Division of Traffic Management), Project P540007-100056 (Signal Installation - Westerville Road at Thornapple Dr./Wallingford Avenue), Object Class 06 (Capital Outlay) per the accounting codes in the attachment to this ordinance.

SECTION 4.  Funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 5.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 6.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 7.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor or ten days after passage if the Mayor neither approves nor vetoes the same.