File #: 2062-2018    Version: 1
Type: Ordinance Status: Passed
File created: 7/10/2018 In control: Public Utilities Committee
On agenda: 7/30/2018 Final action: 8/3/2018
Title: To authorize the Director of Public Utilities to modify and increase the Professional Construction Management Services agreement with URS Corporation - Ohio; for the Division of Water; to authorize a transfer and an expenditure up to $309,000.00 within the Water General Obligations Bond Fund; and to authorize an amendment to the 2018 Capital Improvements Budget. ($309,000.00)
Attachments: 1. ORD 2062-2018 Information, 2. ORD 2062-2018 SWIF, 3. ORD 2062-2018 Amend CIB, 4. ORD 2062-2018 Funding
Explanation

1.0 BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase the Professional Construction Management Services agreement with URS Corporation - Ohio, which provides construction management, field representation, inspection testing, instrumentation/control integration and support services, and services for maintenance of operations during construction for various capital improvements projects for the Division of Water.

The original legislation and contract anticipated that Professional Construction Management services would be provided under multiple contract modifications over a multiyear period to support construction projects that begin construction within the 2011 through 2015 period, with services extending through the end of the subsequent construction duration. As noted in the original legislation, the contract duration may need to be extended based on actual construction durations. Based on current estimated construction schedules, this contract is expected to run from 2010 through mid-2019.

The original legislation, under Ordinance No. 1386-2010, was executed in December 2010 to allow the Professional Construction Management Team to perform a constructability review of the Upground Reservoir R-2 Project prior to advertisement for bid in December 2010.

Modification No. 1, under Ordinance No. 0134-2011, enabled the Professional Construction Management Team to perform construction management and field representation for the Upground Reservoir Raw Water Pump Station and Raw Water Line projects.

Modification No. 2, under Ordinance No. 0975-2011 enabled the Professional Construction Management Team to perform construction management and field representation for various projects, for the remainder of 2011 and the first half of 2012.

Modification No. 3, under Ordinance No. 1487-2012, enabled the Professional Construction Management Team to perform construction management and field representation ...