File #: 2316-2018    Version: 1
Type: Ordinance Status: Passed
File created: 8/15/2018 In control: Public Utilities Committee
On agenda: 9/24/2018 Final action: 9/27/2018
Title: To authorize the Director of Public Utilities to modify (Mod #2) an existing professional engineering services agreement with Hatch Chester (Ohio) Inc. for the Jackson Pike Waste Water Treatment Plant Facilities and Equipment Upgrade for Whittier Street Storm Tanks Project; to authorize the transfer within of $271,819.00 and an expenditure of up to $400,000.00 from the Sanitary Sewer General Obligation Bond Fund, and to amend the 2018 Capital Improvements Budget. ($400,000.00)
Attachments: 1. Ord 2316-2018 17. Director's Legislation Info Sheet, 2. Ord 2316-2018 5. New Utilization Form MASTER (5-2-18), 3. Ord 2316-2018 DAX Financial Form 650258-100001
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to modify (Mod #2) an existing professional engineering agreement with Hatch Chester (Ohio) Inc., for the Jackson Pike Waste Water Treatment Plant (JPWWTP) Facilities and Equipment Upgrade for the Whittier Street Storm Tanks (WSST) Project, CIP 650258-100001. The original intent of this project was to create a design that would fully restore the Whittier Street Storm Tanks and control house. This facility was built in the 1930s and much of the electrical and mechanical equipment has failed, is failing, or is obsolete. The scope requirements for the construction work changed.

This modification will provide additional detailed design work, bid package development, and assistance with bidding and advertisement to reflect the new scope of work. There will be an additional planned renewals for services during construction.

At the conclusion of detailed design, a separate construction contract will be competitively bid and awarded.

1.1. Amount of additional funds to be expended: $400,000.00
Original Contract Amount: $ 425,856.00
Modification #1 $1,079,585.00
Modification #2 (Current) $ 400,000.00
TOTAL Cost ($) $1,905,441.00

(Future -2019) Renewal #1 $1,320,000.00
Proposed Future Total Cost ($) $3,225,441.00

1.2. Reasons additional goods/services could not be foreseen:
This modification will allow for redesign of the 95% drawings. New information allows the City to reduce the scope of work for the construction Contractor. This modification will include redesign, preparation of the contract documents, and assistance for bidding of the construction contract. A future renewal for services during construction will be needed.

1.3. Reason other procurement processes are not used:
The current consultant has intricate knowledge about the facility and the 95% design. Editing the 95% design by the current Consultant will be more economical and efficient...