header-left
File #: 2868-2018    Version: 1
Type: Ordinance Status: Passed
File created: 10/10/2018 In control: Finance Committee
On agenda: 11/19/2018 Final action: 11/21/2018
Title: To authorize the Director of Finance and Management to enter into a contract on behalf of the Office of Construction Management with R.W. Setterlin Building Company for elevator modernization at the Jerry Hammond Center, 1111 E. Broad Street; and to authorize the expenditure of $1,932,000.00 from the Construction Management Capital Improvement Fund. ($1,932,000.00)
Attachments: 1. 2868-2018.pdf

Explanation

 

BACKGROUND:  This legislation authorizes the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with R.W. Setterlin Building Company for elevator upgrades at the Jerry Hammond Center, 1111 E. Broad Street.

This project is for the renovation of six elevators at the Jerry Hammond Center, 1111 E. Broad Street.  These elevators are at the end of their useful life and there is a difficulty in obtaining necessary replacement parts for routine maintenance.  This renovation project will modernize and upgrade the equipment and controls for each elevator, ensuring that all six function as intended. The work also includes ensuring that all elevators and related systems are up to current elevator code.

The Department of Finance and Management, Office of Construction Management, solicited bids for the elevator upgrade at the Jerry Hammond Center, 1111 E. Broad Street. The project was formally advertised.  On September 21, 2018 the city received five (5) bids (0 FBE, 0 MBE) as follows:

 

Company                                                                                    Bid Amount                                          Certification

 R.W. Setterlin Building Company                     $1,932,000.00                                          EBOCC

The Righter Company, Inc.                                          $1,956,000.00                                          EBOCC

Altman General Contractors                                          $1,968,093.00                                          EBOCC

2K General Company                                                               $2,010,000.00                                          EBOCC

Gutknecht Construction Co.                                          $2,044,000.00                                          EBOCC

 

R.W. Setterlin Building Company submitted the lowest bid and the Office of Construction Management therefore recommends the bid award be made to the lowest, most responsive and responsible bidder, R.W. Setterlin Company.

 

R.W. Setterlin Building Company Contract Compliance No. 31-0836188, expiration date February 24, 2019.

 

Fiscal Impact:  This legislation authorizes an expenditure of $1,932,000.00 from the Construction Management Capital Improvement Fund for services related to the elevator upgrades at the Jerry Hammond Center, 1111 E. Broad Street. $2.0 million was budgeted within the Construction Management Capital Improvement Fund for this project.  These funds are contingent upon the 2018 Bond Sale.

 

Title

 

To authorize the Director of Finance and Management to enter into a contract on behalf of the Office of Construction Management with R.W. Setterlin Building Company for elevator modernization at the Jerry Hammond Center, 1111 E. Broad Street; and to authorize the expenditure of $1,932,000.00 from the Construction Management Capital Improvement Fund. ($1,932,000.00)

 

 

Body

 

WHEREAS, there is a need to modernize the existing elevators located at the Jerry Hammond Center, located at 1111 E. Broad street; and

 

WHEREAS, this modernization would include upgrading the equipment and controls for each elevator; and

 

WHEREAS, the Office of Construction Management solicited bids for this project and five firms submitted bids; and

 

WHEREAS, R.W. Setterlin Building Company was deemed the lowest, responsive, and responsible bidder; and

 

WHEREAS, it is necessary to authorize the expenditure of $1,932,000.00 from the Construction Management Capital Improvement Fund; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Finance and Management, Office of Construction Management, to authorize the Finance and Management Department, to enter into a contract with R.W. Setterlin Building Company for services related to elevator upgrades at the Jerry Hammond Center, 1111 E. Broad Street; now, therefore

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS

 

SECTION 1.  That the Finance and Management Director is hereby authorized to enter into a contract on behalf of the Office of Construction Management with R.W. Setterlin Building Company for elevator modernization and upgrades at the Jerry Hammond Center, 1111 E. Broad Street.

SECTION 2.  That the expenditure of $1,932,000.00, or so much thereof as may be necessary in regard to the action authorized in SECTION 3, is hereby authorized in Fund 7732, Construction Management Capital Improvement Fund, in Object Class 06 Capital Outlay per the accounting codes in the attachment to this ordinance.

SECTION 3That the monies in the foregoing sections shall be paid upon order of the Director of Finance and Management, and that no order shall be drawn or money paid except by voucher, the form of which shall be approved by the City Auditor.

 

SECTION 4.  That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 5.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 6That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

SECTION 7That this ordinance shall take effect and be in force from and after the earliest period allowed by law.