Title: To amend the 2018 Capital Improvement Budget; to authorize the Director of Public Service to enter into a contract modification with AECOM Technical Services in connection with the Celebrate1 Sidewalk - Hilltop project; to authorize the expenditure of up to $106,810.00 from the Streets and Highways Bond Fund for the project; and to declare an emergency. ($106,810.00)
Attachments: 1. ORD 3230-2018 Hilltop mod 1 (AECOM)

Explanation

1.  BACKGROUND

This legislation authorizes the Director of Public Service to modify a professional services contract with AECOM Technical Services, Inc., to add additional funds for design of the Celebrate1 Sidewalk - Hilltop contract.

Ordinance 2920-2017 authorized the Director of Public Service to enter into a professional services contract with AECOM Technical Services, Inc., for the Celebrate1 Sidewalk - Hilltop project.  This project consists of the installation of approximately 2,200 feet of sidewalk along Belvidere Avenue between Mound Street and Sullivant Avenue and approximately 5,400 feet of sidewalk along Springmont Avenue/Walsh Avenue between Highland Avenue and Ryan Avenue.  Sidewalk will be installed along one side of both streets.

This is a planned contract modification.  The dollar amount of the original contract was established to allow preliminary engineering to begin, with the intention of adding additional funds to complete design when funding became available.  The contract will be modified to increase funding in the amount of $106,810.00 so the design of the original scope can be completed.

The original contract amount:                                                                             $200,000.00     (PO101606, Ord. 2920-2017)                         

The total of Modification No. 1:                                                                      $106,810.00     (This Ordinance)

The contract amount including all modifications:                            $306,810.00 

 

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against AECOM Technical Services, Inc.

 

2.  CONTRACT COMPLIANCE

The contract compliance number for AECOM Technical Services, Inc., is CC61922-11350 and expires 9/19/2020.

 

3.  FISCAL IMPACT

Funding in the amount of $106,810.00  is available within the Streets and Highways Bond Fund, Fund 7704, within the Department of Public Service.  An amendment to the 2018 Capital Improvements Budget is necessary to align budget authority with the proper project.

 

4.  EMERGENCY DESIGNATION

Emergency action is requested to complete the project in a timely manner to enhance the safety of the travelling public.                     

 

Title

To amend the 2018 Capital Improvement Budget; to authorize the Director of Public Service to enter into a contract modification with AECOM Technical Services in connection with the Celebrate1 Sidewalk - Hilltop project; to authorize the expenditure of up to $106,810.00  from the Streets and Highways Bond Fund for the project; and to declare an emergency.  ($106,810.00)

 

Body

WHEREAS, contract no. PO101606 with AECOM Technical Services, Inc., in the amount of $200,000.00, was authorized by ordinance no. 2920-2017 for the Celebrate1 Sidewalk - Hilltop project; and

 

WHEREAS, it has become necessary to modify the contract in an amount up to $106,810.00 to provide additional funds to complete the original project scope; and

 

WHEREAS, it is necessary to amend the 2018 Capital Improvement Budget to align budget authority with the proper project; and

 

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Service in that it is immediately necessary to authorize the Director to enter into a contract modification with AECOM Technical Services, Inc., to prevent delays in the project schedule to enhance the safety of the travelling public, thereby preserving the public health, peace, safety, and welfare; now, therefore:

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

                     

SECTION 1.  That the 2018 Capital Improvements Budget authorized by Ordinance 1010-2018 be amended to establish sufficient authority for this project:

 

Fund / Project / Project Name / C.I.B. / Change / C.I.B. as Amended

7704 / P590955 - 100028 / CelebrateOne Sidewalk (Voted 2016 Debt SIT Supported) / $300,000.00 / ($106,810.00) / $193,190.00

7704 / P590955 - 100030 / Celebrate1 Sidewalk - Hilltop (Voted 2016 Debt SIT Supported) / $0.00 / $106,810.00  / $106,810.00

 

SECTION 2.  That the Director of Public Service be, and hereby is, authorized to enter into a contract modification with AECOM Technical Services, Inc., 277 West Nationwide Boulevard, Columbus, Ohio, 43215, for the Celebrate1 Sidewalk - Hilltop project in the amount of $106,810.00, or so much thereof as may be needed, in accordance with the plans and specifications on file in the Department of Public Service, which are hereby approved.

SECTION 3.  That the expenditure of $106,810.00, or so much thereof as may be needed, is hereby authorized in Fund 7704 (Streets and Highways Bond Fund), Dept-Div 5911 (Infrastructure Management), Project P590955 - 100030 (Celebrate1 Sidewalk - Hilltop), in Object Class 06 (Capital Outlay) per the accounting codes in the attachment to this ordinance.

 

SECTION 4.  That the funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 5.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 6.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 7.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor or ten days after passage if the Mayor neither approves nor vetoes the same.