Title: To authorize the Director of Public Utilities to enter into an agreement with Carpenter Marty Transportation, Inc., for professional engineering services for the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects for the Division of Power; to authorize a transfer and expenditure up to $186,366.09 within the Electricity General Obligations Bonds Fund; and to authorize an amendment to the 2018 Capital Improvements Budget. ($186,366.09)
Attachments: 1. ORD 3245-2018 Information, 2. ORD 3245-2018 Utilizations, 3. ORD 3245-2018 maps, 4. ORD 3245-2018 Funding

Explanation

 

1. BACKGROUND:  This legislation authorizes the Director of Public Utilities to enter into professional engineering services agreements with Carpenter Marty Transportation, Inc. for the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects for the Division of Power.

 

DESCRIPTION:  These 2 projects are from a total of 8 the Division of Power advertised under the 2018 Streetlight Design Project.  The proposed streetlights will incorporate LED technology that will generate savings in electric energy and long-term maintenance which will be a significant economic impact and reduce greenhouse gases to the environment.  Additionally, the proposed projects will greatly improve the aesthetics of the affected areas.

 

Broad Street and Noe Bixby Road Street Lighting, CIP No. 670851-100000:

This project will design a new underground street lighting system in the Broad Street/Noe Bixby Road area.  Existing luminaires will be replaced with LED luminaires. 

 

The community planning area is “21 - Far East” and includes Broad Street between the river and Taylor Station Road and Noe Bixby Road between Bastille Place and Broad Street.

 

Jasonway & Knightsbridge Street Lighting, CIP No. 670853-100000:

This project will design a new overhead street lighting system for the Jasonway & Knightsbridg area.

 

The community planning area is “05 - Northwest” and includes Jasonway Avenue between Olentangy River Road and Shuster Lane, Knightsbridge Boulevard between Henderson Road and Olentangy River Road, and Olentangy River Road between the SR 315 ramp and Bethel Road.

 

TIMELINE:  The term of both engineering agreements is for 1 year and is expected to end November 2019.

 

PROJECT AMOUNTS:

Broad St. and Noe Bixby Rd. Street Lighting, (CIP 670851):  $102,960.72

Jasonway & Knightsbridge Street Lighting (CIP 670853):  $83,405.37

 

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: 

The projects will replace outdated street lighting which will result in an energy consumption savings for the City of Columbus.  The addition of street lighting to the area may provide a sense of security to the residents, deter crime, and minimize potential impacts to City safety services. 

 

3. BID INFORMATION:  The selection of the firm providing the professional engineering services has been performed in accordance with the procedures set forth in Columbus City Code, Section 329, "Awarding professional service contracts through requests for proposals."  The evaluation criteria for this contract included:  1. Understanding of the Project, 2. Environmentally Preferable, 3. Past Performance, and 4. Local Workforce.

 

On August 3, 2018, the Department received four proposals from:  EMH&T, Dynotec, Patrick Engineering, and Carpenter Marty Transportation.

 

An evaluation committee reviewed the proposals and scored them based on the criteria mentioned above.  The Department of Public Utilities recommends that the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects be awarded to Carpenter Marty Transportation, Inc.

 

The Contract Compliance Number for Carpenter Marty Transportation, Inc. is 46-0918246 (expires 8/15/19, MAJ, DAX No. 8494). 

 

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Carpenter Marty Transportation, Inc.

 

4. FISCAL IMPACT: A transfer of funds within the Electricity G.O. Bonds Fund will be necessary as well as an amendment to the 2018 Capital Improvements Budget.

 

 

 

Title

 

To authorize the Director of Public Utilities to enter into an agreement with Carpenter Marty Transportation, Inc., for professional engineering services for the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects for the Division of Power; to authorize a transfer and expenditure up to $186,366.09 within the Electricity General Obligations Bonds Fund; and to authorize an amendment to the 2018 Capital Improvements Budget.  ($186,366.09)

 

 

Body

 

WHEREAS, four technical proposals for professional engineering services for the 2018 Streetlight Design Project were received on August 3, 2018; and

 

WHEREAS, the 2018 Streetlight Design Project contains eight separate street lighting projects; and

 

WHEREAS, the Department of Public Utilities recommends that the agreements for the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects be awarded to Carpenter Marty Transportation, Inc.; and

 

WHEREAS, it is necessary to authorize a transfer and expenditure of funds within the Electricity G.O. Bonds Fund, for the Division of Power; and 

 

WHEREAS, it is necessary to authorize an amendment to the 2018 Capital Improvements Budget for purposes of providing sufficient funding and expenditure authority for the aforementioned project expenditures; and

 

WHEREAS, it has become necessary in the usual daily operation of the Division of Power, Department of Public Utilities, to authorize the Director of Public Utilities to enter into professional engineering services agreement with Carpenter Marty Transportation, Inc. for the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects, all for the preservation of the public health, peace, property and safety; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities is hereby authorized to enter into professional engineering services agreements with Carpenter Marty Transportation, Inc. (FID# 46-0918246), 6612 Singletree Drive, Columbus, Ohio 43229; for the Broad Street and Noe Bixby Road and Jasonway & Knightsbridge Street Lighting Improvements Projects; for an expenditure up to $186,366.09 in accordance with the terms and conditions of the contracts on file in the Office of the Division of Power.

 

SECTION 2. That the transfer of $186,366.09 or so much thereof as may be needed, is hereby authorized between projects within 6303 - Electricity G.O. Bond Fund, per the account codes in the attachment to this ordinance.

 

SECTION 3.  That the 2018 Capital Improvements Budget is hereby amended, in Fund 6303 - Electricity G.O. Bonds Fund, as follows:

 

Project No. | Project Name | Revised Authority | Remaining Authority | Change

P670003-100200 (carryover) | DOP Large Scale Development | $1,791,152 | $1,604,786 | -$186,366

P670851-100000 (carryover) | Broad/Noe Bixby SL Imp's | $0 | $102,961 | +$102,961                     

P670853-100000 (carryover) | Jasonway/Knightsbridge SL Imp's | $0 | $83,405 | +$83,405

 

SECTION 4. That an expenditure of $186,366.09 or so much thereof as may be needed, is hereby authorized in Fund 6303 - Electricity G.O. Bonds Fund, in Object Class 06 - Capital Outlay, per the accounting codes in the attachment to this ordinance.

 

SECTION 5.  That the funds necessary to carry out the purpose of this Ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 6.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

 

SECTION 7.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 