header-left
File #: 1231-2019    Version: 1
Type: Ordinance Status: Passed
File created: 4/26/2019 In control: Public Service & Transportation Committee
On agenda: 5/20/2019 Final action: 5/22/2019
Title: To authorize the Director of Public Service to enter into a contract modification with Complete General Construction Company in connection with the Bridge Rehabilitation - Annual Citywide Contract (2017) project; to authorize the expenditure of up to $117,300.00 from the Streets and Highways Bond Fund to pay for the modification; and to declare an emergency. ($117,300.00)
Attachments: 1. ORD 1231-2019 mod 3 BR-Annual Citywide Contract 2017
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to modify and increase an existing contract with Complete General Construction Company for the Bridge Rehabilitation - Annual Citywide Contract (2017) project and provide additional funds for construction inspection and administration.

Ordinance 3133-2017 authorized the Director of Public Service to enter into a contract with Complete General Construction Company for the construction of the Bridge Rehabilitation - Annual Citywide Contract (2017) project and to provide for construction administration and inspection services. The work for the project consists of the routine maintenance of several bridges within the City of Columbus.

Ordinance 0683-2018 authorized the Director of Public Service to enter into a contract modification with Complete General Construction Company for the Bridge Rehabilitation - Annual Citywide Contract (2017) project and to provide for construction administration and inspection services. The work for the modification consisted of a lighting upgrade project to the Broad Street Bridge.

Ordinance 1437-2018 authorized the Director of Public Service to enter into a contract modification with Complete General Construction Company for the construction of the Bridge Rehabilitation - Annual Citywide Contract (2017) project and to provide for construction administration and inspection services. The work for the modification completed the lighting upgrade project to the Broad Street Bridge.

This ordinance will add funding to complete the work for the original Bridge Rehabilitation - Annual Citywide Contract (2017) projects that were put on hold due to the additional costs associated with the lighting upgrade for the Broad Street Bridge, as well as additional funds for construction inspection and administration.

The original contract amount: $1,450,000.00 (PO095746, Ord. 3133-2017)
The total of Modif...