Explanation
1. BACKGROUND
The Division of Infrastructure Management is engaged in the Alley Rehabilitation project for the rehabilitation of city alleys. As part of this project, Division of Infrastructure Management crews will perform work such as clearing, surface grading, leveling, drainage improvements, and selective repaving.
The rehabilitation of these alleys requires several commodities. The Purchasing Office has solicited formal competitive bids for the purchase of these commodities and has established universal term contracts (UTC). It is necessary to establish funding in the amount of $200,000.00 for this purpose.
The Director of Finance and Management is hereby authorized to associate all General Budget Reservations resulting from this ordinance with the appropriate Universal Term Contract Purchase Agreements listed below for Pavement Materials & Aggregates for the Division of Infrastructure Management from established, pending and future universal term contracts.
Universal Term Contract Purchase Agreements:
Asphalt Emulsions
Portland Cement
Various Asphalt Concrete
Crushed Limestone & Gravel Agg.
Winter Asphalt
Crack Sealing Product
The following Purchase Agreement associations require approval by City Council in order for the division to expend more than $100,000.00, per 329.19(g): Pavement Materials & Aggregates.
2. FISCAL IMPACT
Although this purchase was not originally budgeted in the Street Construction, Maintenance, and Repair Fund (Fund 2265), the aggregate is needed, and the fund has the available resources to make this purchase.
3. EMERGENCY DESIGNATION
Emergency legislation is requested to have funding available for this project so materials purchases can be made at the earliest possible time.
Title
To appropriate $200,000.00 from the unappropriated balance of the Street, Construction, Maintenance, and Repair Fund; to authorize the Director of Finance and Management to associate all General B...