File #: 2136-2020    Version: 1
Type: Ordinance Status: Passed
File created: 9/16/2020 In control: Public Utilities Committee
On agenda: 10/12/2020 Final action: 10/15/2020
Title: To authorize the Director of Public Utilities to modify (Mod #3) an existing professional engineering services agreement with Hatch Associates Consultants, Inc. for the Jackson Pike Waste Water Treatment Plant Facilities and Equipment Upgrade for Whittier Street Storm Tanks Project; and to authorize the expenditure of up to $1,198,635.18 from the Sewer General Obligation Bond Fund.
Attachments: 1. ORD 2136-2020 Funding Template, 2. ORD 2136-2020 Utilization
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to modify (Mod #3) an existing professional engineering agreement with Hatch Associates Consultants, Inc., for the Jackson Pike Waste Water Treatment Plant (JPWWTP) Facilities and Equipment Upgrade for the Whittier Street Storm Tanks (WSST) Project, CIP 650258-100001. The original intent of this project was to create a design that would fully restore the Whittier Street Storm Tanks and control house. This modification is for needed engineering services during construction to ensure that design intents are met during this complex and large construction project. This modification for services during construction is planned for third quarter 2020 and will progress through the duration of construction. The separate construction project is expected to be completed by fourth quarter of 2023.

Community Planning Area is 99 Citywide.

1.1. Amount of additional funds to be expended: $1,198,635.18
Original Contract Amount: $ 425,856.00
Modification #1 $1,079,585.00
Modification #2 $ 400,000.00
Modification #3 (current) $1,198,635.18
TOTAL Cost ($) $3,104,076.18


1.2. Reasons additional goods/services could not be foreseen:
This is a planned modification as the services were foreseen.

1.3. Reason other procurement processes are not used:
This is a planned modification of an existing contract.

1.4. How cost of modification was determined:
The cost proposal was provided by Hatch Associates Consultants, Inc., reviewed by the Division of Sewerage, and Drainage and was deemed acceptable.

2. PROJECT TIMELINE: This modification for services during construction is planned for third quarter 2020 and will progress through the duration of construction. The separate construction project is expected to be completed by fourth quarter of 2023.

3. DESIGNATION: Emergency designation is not requested at this time.

4. CONTRACT COMPLIANCE N...