Title: To authorize the Director of Public Utilities to enter into a construction contract with General Temperature Control, Inc. for the Southerly Wastewater Treatment Plant Building Heat Improvements/Underground Storage Tank Removal Project; to authorize the appropriation and transfer of $5,486,800.00 from the Sanitary Sewer Reserve Fund to the Ohio Water Development (OWDA) Loan Fund; to authorize the appropriation and expenditure of $5,486,800.00 from the Ohio Water Development (OWDA) Loan Fund; to authorize an expenditure up to $2,000.00 for prevailing wage services to the Department of Public Services within the Sanitary General Obligations Voted Bonds Fund; to amend the 2020 Capital Improvement Budget; and to declare an emergency. ($5,488,800.00)
Attachments: 1. ORD 2991-2020 Utilization, 2. ORD 2991-2020 Funding Template

Explanation

 

BACKGROUND: This project will remove three (3) fuel oil Underground Storage Tanks (USTs) at the Southerly Waste Water Treatment Plant.  This work will include removal and proper disposal of the USTs, all associated piping, and connected boilers, as well as any improvements required to update the affected heating systems and eliminate reliance on the fuel oil.

 

Community Planning Area: 99 Citywide

 

PROJECT TIMELINE: Contract work is required to be substantially complete in a manner acceptable to the City within 500 days from the date that a Notice To Proceed (NTP) is given by the City.

 

PROCUREMENT INFORMATION: The Division advertised for competitive bids submission for the subject services on the City's Vendor Services website and in the City Bulletin in accordance with the overall provisions of Chapter 329 of the Columbus City Code. The Division of Sewerage and Drainage received one (1) bid on November 18, 2020 from the following company:

 

NAME

TAX ID

DAX #

City/State

Status

Expiration

General Temp. Control

31-1201236

004830

Canal Winchester, OH

MAJ

9/30/2022

 

 

EMERGENCY DESIGNATION is requested for this project in order to meet project time lines and deliverables.

 

ECONOMIC / ENVIRONMENTAL IMPACT: This project will help the Southerly Wastewater Treatment Plant to be compliant with the well field protection chapter of the Columbus City Code, by eliminating 3 USTs from the site. 

FISCAL IMPACT: This Ordinance authorizes the City Auditor to appropriate and transfer funds from the Sanitary Sewer Reserve Fund 6102 to the Ohio Water Development (OWDA) Loan Fund 6111 in order to fund this expenditure.  This transaction is a temporary measure that is required until such time as the division is able to execute a loan with the OWDA Loan Fund and reimburse the Sanitary Sewer Reserve Fund.  The loan is expected to be approved in January 2021.  Additionally $2,000.00 is necessary for Prevailing Wage Services from the Department of Public Service.  The expenditure of $2,000.00 is needed from the Sanitary Sewer General Obligation Bond Fund 6109.  An amendment to the 2020 Capital Improvement Budget is also necessary to align the authority.

 

Title

 

To authorize the Director of Public Utilities to enter into a construction contract with General Temperature Control, Inc. for the Southerly Wastewater Treatment Plant Building Heat Improvements/Underground Storage Tank Removal Project; to authorize the appropriation and transfer of $5,486,800.00 from the Sanitary Sewer Reserve Fund to the Ohio Water Development (OWDA) Loan Fund; to authorize the appropriation and expenditure of $5,486,800.00 from the Ohio Water Development (OWDA) Loan Fund; to authorize an expenditure up to $2,000.00 for prevailing wage services to the Department of Public Services within the Sanitary General Obligations Voted Bonds Fund; to amend the 2020 Capital Improvement Budget; and to declare an emergency. ($5,488,800.00)

 

 

Body

 

WHEREAS, the Division of Sewerage and Drainage advertised for competitive bids for the Southerly Wastewater Treatment Plant Building Heat Improvements/Underground Storage Tank Removal Project CIP# 650260-103002, and one (1) bid were received on November 18, 2020; and

 

WHEREAS, it is necessary to authorize the Director of the Department of Public Utilities to execute a construction contract with General Temperature Control, Inc. and to encumber and expend funds to provide for prevailing wage services for the Division of Sewerage and Drainage’s Southerly Wastewater Treatment Plant Building Heat Improvements/Underground Storage Tank Removal Project, CIP# 650260-103002; and

 

WHEREAS, it is necessary to both appropriate funds from the Sewer System Reserve Fund 6102 and to authorize the transfer of said funds to the OWDA Loan Fund 6111 in order to temporarily fund this expenditure until such time as the City receives loan proceeds for the above stated purpose and reimburses the Sewer System Reserve Fund; and

 

WHEREAS, the City anticipates incurring certain Original Expenditures (as defined in Section 1.150-2(c) of the Treasury Regulations (the “Treasury Regulations” promulgated pursuant to the Internal Revenue Code of 1986, as amended)) with respect to the construction of the Project described in this Ordinance (collectively, the “Project”); and

 

WHEREAS, it is necessary to authorize the expenditure of up to $2,000.00 within the Sanitary G.O. Voted Bonds Fund 6109 for Prevailing Wage Services to the Department of Public Service; and 

 

WHEREAS, it is necessary to authorize an amendment to the 2020 Capital Improvement Budget; and 

 

WHEREAS, an emergency exists in the usual daily operations of the Department of Public Utilities in that it is immediately necessary to authorize the Director to enter into a construction contract with General Temperature Control, Inc. in order to meet project deadlines and deliverables, for the preservation of the public health, peace, property, and safety; now, therefore

 

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities is hereby authorized to enter into a construction contract with General Temperature Control, Inc., 970 W Walnut Street, Canal Winchester, OH 43110; for the Division of Sewerage and Drainage’s Southerly Wastewater Treatment Plant Building Heat Improvements/Underground Storage Tank Removal Project, CIP#650260-103002, in accordance with the terms and conditions as shown in the agreement on file in the office of the Division of Sewerage and Drainage; and to obtain the necessary prevailing wage services from the Department of Public Services up to a maximum amount of $2,000.00.

 

SECTION 2.  That from the unappropriated monies in the Sanitary Sewer Reserve Fund 6102 and from all monies estimated to come into said fund from any and all sources, and unappropriated for any other purpose during the fiscal year ending December 31, 2020, the sum of $5,486,800.00 is appropriated in Fund 6102, per the account codes in the funding attachment to this ordinance.

 

SECTION 3.  That the transfer of $5,486,800.00 or so much thereof as may be needed, is hereby authorized between the Sanitary Sewer Reserve Fund 6102 and OWDA Loan Fund 6111 per the accounting codes in the attachment to this ordinance.

 

SECTION 4.  That the expenditure of $5,488,800.00, inclusive of $2,000.00 to the Department of Public Service for prevailing wage services, or so much thereof as may be needed, is hereby authorized per the accounting codes in the attachment to this ordinance.

 

SECTION 5.  That the 2020 Capital Improvement Budget is amended as follows:

 

Fund |  CIP#   |   Project Name     |   Current Authority  | Revised Authority  | Net Change

6111 | 650260-102015 | JPWWTP Raw Sewage Pump Valve Actuator Replacement| $900,000 | $0 | -$900,000

6111 | 650260-103004 | SWWTP Boiler System Operational Improvements | $1,180,115 | $769,080 | -$411,035

6111 | 650260-103002 | SWWTP Building Heating Improvements/Underground Storage Tank Removal | $4,175,765 | $5,486,800 | +$1,311,035

 

SECTION 6.  That the said company, General Temperature Control, Inc., shall perform the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Sewerage and Drainage.

 

SECTION 7.  That the City Auditor is hereby authorized to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project; except that no transfer shall be made from a project by monies from more than one source.

 

SECTION 8.  That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 9.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

SECTION 10.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 11.  That upon obtaining other funds for the purpose of funding sanitary sewer system capital improvement work, the City Auditor is hereby authorized to repay the Sanitary Sewer Reserve Fund the amount transferred above (Section 3), and said funds are hereby deemed appropriated for such purposes.

 

SECTION 12.  That the City intends that this Ordinance constitute an "official intent" for purposes of Section 1.150-2(e) of the Treasury Regulations, and that the City reasonably expects to reimburse itself for certain Original Expenditures incurred with respect to the Project from the proceeds of obligations to be issued by the City in a principal amount currently estimated to be $5,486,800.00 (the "Obligations").

 

The City intends to make a reimbursement allocation on its books for the Original Expenditures not later than eighteen months following the later to occur of the date of the Original Expenditure to be reimbursed or the date the Project for which such Original Expenditures were made is "placed in service" within the meaning of Treasury Regulations Section 1.150-2(c).  Upon the issuance of the Obligations, the proceeds of such Obligations shall be used to reimburse Sanitary/Sewer Reserve Fund 6102, which is the fund from which the advance for costs of the Project will be made.

 

SECTION 13.  That for the reasons stated in the preamble hereto, which is made a part hereof, this Ordinance is declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten (10) days after passage if the Mayor neither approves nor vetoes this Ordinance.