1. BACKGROUND
This ordinance authorizes the Director of Public Service to enter into contract with George J. Igel & Company for the Roadway Improvements - Scioto Peninsula project and to provide payment for construction, construction administration and construction inspection services.
This contract includes reconstructing Capital Street, Rush Alley, and Chapel Street from Starling Street to Belle Street; State Street from the railroad tracks to Belle Street; and Starling Street and Belle Street from Broad Street to Town Street. Project work also includes storm sewer, street lighting, landscaping features, granite curb, sidewalks, paver parking, permeable paver roadways, and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.
The estimated Notice to Proceed date is February 12, 2021. The project was let by the Office of Support Services through Vendor Services and Bid Express. Five bids were received on December 10, 2020, and tabulated as follows:
Company Name Bid Amount City/State Majority/MBE/FBE
George J. Igel & Co. $ 9,321,800.52 Columbus, OH Majority
Shelly & Sands, Inc. $ 9,608,146.01 Columbus, OH Majority
Complete General Construction $ 9,723,436.63 Columbus, OH Majority
Trucco Construction Co. $ 9,896,882.63 Columbus, OH Majority
Catts Construction, Inc. $10,506,956.13 Warrensville Heights, OH Majority
Award is to be made to George J. Igel & Company as the lowest responsive and responsible and best bidder for their bid of $9,321,800.52. The Department of Public Service, Division of Design and Construction, has requested the project contingency amount be increased from 10% to 15%. Therefore the amount of the contract with George J. Igel & Company will increase to $9,745,518.72. The amount of construction admin...