File #: 0286-2021    Version: 1
Type: Ordinance Status: Passed
File created: 1/29/2021 In control: Public Utilities Committee
On agenda: 3/1/2021 Final action: 3/5/2021
Title: To authorize the Director of Public Utilities to execute a planned modification of the 2020-2022 Construction Administration and Inspection Services Agreement with Stantec Consulting Services for a Division of Sewerage and Drainage project; to authorize an expenditure of up to $150,000.00 from the Sanitary General Obligation Bond Fund; and to authorize an amendment the 2020 Capital Improvements Budget. ($150,000.00)
Attachments: 1. ORD 0286-2021 Funding Template, 2. ORD 0286-2021 Utilization
Explanation

1.0 BACKGROUND:
This legislation authorizes the Director of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration and Construction Inspection (CA/CI) Services agreement with Stantec Consulting Services, Inc.

Funding for this modification will be for the following Division of Sewerage & Drainage project:
Alum Creek Trunk (Middle) Rehabilitation - Phase B CIP #:650725-100015

1.1. Amount of additional funds to be expended: $150,000.00

Original Agreement Amount: $ 198,538.62 PO221581/PO221595
Modification 1: $ 395,138.19 PO222666/PO222668/PO222669
Modification 2: $ 248,287.56 PO225314
Modification 3: $ 546,494.33 PO236842
Modification 4: $ 484,214.84 PO249724/PO249728/PO249729
Modification 5: $ 150,000.00 Current
Total Original + all Mods: $ 2,022,673.54


1.2. Reasons additional goods/services could not be foreseen:
This is a three-year agreement for fiscal years 2020 - 2022 and modifications were anticipated and explained in the original legislation under Ordinance No. 0130-2020.

1.3. Reason other procurement processes are not used:
This is a multiyear contract that will be modified as required to provide construction administration/inspection services for construction projects that bid during the three year (2020-2022) timeframe.

1.4. How cost of modification was determined:
The cost of Modification No. 5 was determined by negotiations between Stantec Consulting Services Inc. and the Division of Sewerage & Drainage.

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT:
Division of Water projects include replacement or rehabilitation of water lines that have a high break frequency and valves that are inoperable. Replacement of these water lines will improve water service, decrease burden on water maintenance operations, and reduce water loss. The Neighborhood Liaison(s) will be contacted and...