File #: 0801-2021    Version: 1
Type: Ordinance Status: Passed
File created: 3/24/2021 In control: Public Utilities Committee
On agenda: 4/26/2021 Final action: 4/29/2021
Title: To authorize the Director of Public Utilities to renew the service contract with Atlas-SSI, Inc. for the removal and upgrade of intake water screens at the Dublin Road Water Plant; for the Division of Water; to authorize a transfer and expenditure up to $150,700.00 within the Water General Obligations Bond Fund; and to authorize an amendment to the 2020 Capital Improvements Budget. ($150,700.00)
Attachments: 1. ORD 0801-2021 Information, 2. ORD 0801-2021 Map, 3. ORD 0801-2021 Funding
Explanation

1. BACKGROUND: This Ordinance authorizes the Director of Public Utilities to renew the service contract with Atlas-SSI, Inc. for the removal and upgrade of raw water screens at the Dublin Road Water Plant, Capital Improvements Project No. 690278-100000, Division of Water Contract No. 2330.

The overall contract will rehabilitate up to three raw water screens at the Dublin Road Water Treatment Plant. Rehabilitation will include removal of the screen, shipment to the vendor’s facility, removal of existing coatings and installation of new coatings, and replacement of wear parts with new parts, shipment back to the plant, and reinstallation.

The first screen was rehabilitated in 2020 (PO238974), the second screen will be rehabilitated in 2021 (this renewal) and the third screen will be rehabilitated in 2022 (renewal #2).

The Community Planning Area is “99 - Citywide” since the DRWP serves multiple planning areas.

1.1 Amount of additional funds to be expended: $150,700.00
Original Contract Amount: $ 137,170.00 (PO238974)
Renewal No. 1 (current): $ 150,700.00
Total (Orig. + Ren. #1) $ 287,870.00

1.2. Reason other procurement processes are not used:
The initial contract anticipated rehabilitation of three raw water screens, with one screen being rehabilitated under the initial contract, the second screen under renewal #1, and the third screen under renewal #2. Bidding out the work for screen #2 would deviate from the initial contract, require additional effort by the City, and increase the cost and time to rehabilitate the screen.

1.3. How cost of renewal was determined:
The renewal cost was determined by taking the price for the base scope of work outlined in the initial contract ($124,700.00), adding the cost of the additional required work that was not anticipated in the initial contract ($12,300.00) and then including a 10% contingency.

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGE...