File #: 1113-2021    Version: 1
Type: Ordinance Status: Passed
File created: 4/26/2021 In control: Public Service & Transportation Committee
On agenda: 6/7/2021 Final action: 6/10/2021
Title: To authorize the Director of Public Service to enter into agreements with, and to accept funds from, the Franklin County Engineer’s Office relative to the Roadway - Shook Road Phase II project; to authorize the Director of Public Service to refund any sum received in excess of the proportionate share of eligible construction costs to be borne by the Franklin County Engineer’s Office; and to declare an emergency. ($0.00)

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Service to execute agreements with and to accept deposits and/or reimbursements from the Franklin County Engineer’s Office for work performed as part of the Roadway - Shook Road Phase II project.

The aforementioned effort will culminate in the widening of Shook Road north of SR 317 to provide a southbound right turn lane, the widening of SR 317 to provide both westbound and eastbound left turn lanes at the intersection, the construction of a sidewalk along the west and east sides of Shook Road from SR 317 north to existing sidewalk limits, and various other improvements. As part of that effort, the Department of Public Service has agreed to resurface the southbound lane of Shook Road from SR 317 to a point 671 feet south of SR 317 at the behest of the Franklin County Engineer’s Office, which will reimburse the City for the cost of work, presently estimated to be $17,242.74.

This ordinance also authorizes, as necessary, the issuance of a refund of any sum received in excess of the proportionate share of eligible construction costs to be borne by the Franklin County Engineer’s Office.  The refund is to be issued after final accounting for the project is complete or upon certification from the Department of Public Service, Division of Design and Construction, that any funds remaining on deposit from the Franklin County Engineer's Office are not needed and can be refunded.

2.  FISCAL IMPACT

Pursuant to preliminary cost estimates, the Franklin County Engineer’s Office has agreed to reimburse the Department of Public Service for costs incurred relative to resurfacing the southbound lane of Shook Road, with the understanding that the actual amount owed for that purpose may vary based upon the apparent low bid and final quantities. A separate ordinance authorizing the award of a construction contract and the encumbrance and expenditure of City funds to support the construction costs will be put forth for consideration by City Council at a later time. 

 

3.  EMERGENCY DESIGNATION

Emergency action is requested so as to prevent avoidable delays in the completion of necessary public infrastructure improvements. 

Title

To authorize the Director of Public Service to enter into agreements with, and to accept funds from, the Franklin County Engineer’s Office relative to the Roadway - Shook Road Phase II project; to authorize the Director of Public Service to refund any sum received in excess of the proportionate share of eligible construction costs to be borne by the Franklin County Engineer’s Office; and to declare an emergency. ($0.00)

 

Body

WHEREAS, the Department of Public Service is administering the Roadway - Shook Road Phase II project, which encompasses various improvements to Shook Road in the vicinity of SR 317; and

WHEREAS, as part of that effort, the Department of Public Service has agreed to resurface the southbound lane of Shook Road from SR 317 to a point 671’ south of SR 317 at the behest of the Franklin County Engineer’s Office; and 

WHEREAS, this ordinance authorizes the Director of Public Service to execute a reimbursement agreement, or other such agreement(s) as may be necessary, with the Franklin County Engineer’s Office, whereby the Franklin County Engineer’s Office agrees to reimburse the Department of Public Service for the actual costs incurred during the completion of the aforementioned work, and to, as necessary, refund any sum received in excess of the proportionate share of construction costs to be borne by the Franklin County Engineer’s Office; and

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Service in that it is immediately necessary to authorize the Director to enter into agreements with Franklin County so as to prevent delays in the completion of necessary public infrastructure improvements, thereby preserving the public health, peace, property, safety and welfare; now, therefore,

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Service be and hereby is authorized to enter into agreements with, and to accept funds from, the Franklin County Engineer’s Office for the cost of certain work performed during the completion of the Roadway - Shook Road Phase II project.

SECTION 2.  That the Director of Public Service be and is hereby authorized to refund any sum received in excess of the proportionate share of eligible construction costs to be borne by the Franklin County Engineer’s Office.  The refund is to be issued after final accounting for the project is complete or upon certification from the Department of Public Service, Division of Design and Construction, that any funds remaining on deposit from the Franklin County Engineer's Office are not needed and can be refunded.

SECTION 3.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the mayor, or ten days after passage if the mayor neither approves nor vetoes the same.